Another Blown Deadline: For Now, No “New Route” for Northern Pass

Jan 3, 2013 by  | Bio |  Leave a Comment

New Year's Eve in Times Square (photo credit: flickr/Mondayne)

The ball and other ceremonial objects have dropped, and 2013 has arrived. Although we mark the turn of the year with champagne, Auld Lang Syne, and a bevy of news stories and year-end blog posts, there’s not much genuinely “new” about the New Year. We hang a new calendar and start writing 2013 on legal briefs and checks (as the case may be), and life goes on.

Here in New Hampshire, the developer of the Northern Pass transmission project celebrated New Year’s Eve without any year-end changes. As revelers made their way to New Year’s Eve parties, in a classic “news dump” to minimize attention, Northern Pass Transmission LLC (NPT) posted a cryptic “project update” to its website. The update stated:

[W]e have identified a new route in the North Country that we will submit to the New Hampshire Site Evaluation Commission [sic] in the future for consideration and review.  We are in the process of finalizing this new proposal and will soon be prepared to announce its specific details….

We also recognize that while we are communicating with local citizens, stakeholders and public officials across New Hampshire, there is still much that can be done.  We believe this communication and dialogue is critical to the ultimate success of the new route and the project overall and felt it was necessary to take some additional time to continue these efforts before we publicly announce the new routing proposal.

In other words, NPT and its parent company Northeast Utilities (NU) had nothing new to announce, and the public will continue to wait for actual details and updated regulatory filings. And it’s not the first time Northern Pass’s developer has failed to deliver on its promise of a new route.

In May, NU set an August deadline for a route announcement; in July, NU set a September deadline; and throughout the fall, NU promised to finalize a route and file an updated Presidential Permit application with the U.S. Department of Energy by the end of the 2012, even going so far as to say that it had already obtained 99% of the land it needs. In this context, the Concord Monitor aptly reported on the New Year’s Eve “update”: Northern Pass misses deadline to unveil new route.

While NPT’s non-announcement wasn’t a surprise to CLF or others following the project closely, it was an important moment. It was, most of all, an embarrassing setback – the latest blown deadline after a series of blown deadlines stretching back to April 2011, when NPT decided to seek out a “new route” for the northernmost portion of the project.

NPT has been banking on its capacity to pay above-market land prices for a transmission corridor in the North Country. So far, the Society for the Protection of New Hampshire Forests, its supporters from more than two hundred New Hampshire towns and cities and also from around the region and country, and a number of courageous landowners unwilling to sell at any price have achieved remarkable success in blocking NPT’s efforts on the ground, property-by-property. It would appear NPT’s confidence was misplaced.

For NU executives and investors, Hydro-Québec, and Northern Pass enthusiasts in southern New England, the project’s latest blown deadline should be a wake-up call.

It’s not working.

Not NPT’s back-room strategy to assemble a serpentine series of parcels for a new transmission corridor in the North Country, without any meaningful changes to the project’s design or the southern 80% of its proposed route.

Not NPT’s attempts to game the federal permitting process in its favor.

Not NPT’s bogus claims of environmental and economic benefits for New Hampshire and of wide support for the project.

Not NPT’s campaign to discredit affected citizens in the nearly three dozen communities that have declared opposition to the project and the entire New Hampshire conservation community as “not in my backyard” types and “special interests.”

In the New Year, Northern Pass’s developers should recognize that half of the “dialogue” they are promising is listening. The latest blown deadline should signal, loud and clear, that the current Northern Pass proposal won’t be successful, new route in Coös County or not.

The Latest on Northern Pass: A Year-End Roundup

Dec 28, 2012 by  | Bio |  Leave a Comment

As CLF begins a third year of advocacy on the Northern Pass project, some updates are in order:

The “New Route” Drama

With 2013 only days away, it is looking more and more likely that Northern Pass Transmission LLC (NPT) will not have secured 100% of a “new route” for the project’s northernmost portion by year end, as its public statements have been promising for months. As chronicled in a Boston Globe front-page story published earlier this week (the national daily’s first major story on Northern Pass), landowners are rejecting repeated offers from NPT, and our friends at the Society for the Protection of New Hampshire Forests have secured agreements to conserve key parcels along what appears to NPT’s preferred new path. (According to report in yesterday’s Union Leader, NPT officials are readying some kind of “update” on the project’s progress, which may raise more questions than it answers.)

If NPT fails to make good on its promised “new route,” it will be a singular embarrassment and signal more wasted months of self-inflicted delay. It also will continue NPT’s troubling pattern of misleading investors and peddling falsehoods about the project.

Whatever the success of NPT’s attempt to buy a transmission corridor through New Hampshire’s North Country, Northern Pass overall will remain the same flawed proposal that affected communities and stakeholders have overwhelmingly rejected over the last two years. Susan Arnold of the Appalachian Mountain Club and I penned an op-ed with this message, and it was widely published in New Hampshire newspapers this month. Please take a moment to read the op-ed here.

NU’s False Statements Get Noticed

Over the last month, the Boston Globe, the Concord Monitor, Connecticut newspapers, and NHPR (complete with audio) published stories on Northeast Utilities CEO Tom May’s blatantly false statements about support for Northern Pass. Instead of correcting the comments, NU’s spokesperson compounded Mr. May’s misstatements by insisting, contrary to any possible interpretation of the comments, that Mr. May was speaking about support for the Cape Wind project – a renewable energy proposal backed by a strong public campaign that is co-sponsored by many of the region’s environmental groups. The contrast with Northern Pass couldn’t be starker.

A Broken Permitting Process

The Department of Energy’s permitting process for the Northern Pass project remains tainted by its abdication of responsibility to select an independent and impartial contractor to prepare the crucial environmental impact statement for the project. In a recent letter to Senator Shaheen, DOE repeated its prior position that it sees nothing wrong with the way the current contractor team was selected because NPT’s extraordinary role in the selection process was not unusual. As I explained in October, a precedent of repeating a mistake is no justification. In November, CLF filed a new Freedom of Information Act request to understand the activities of the contractor team, DOE, and NPT during the last year and the extent of NPT’s influence over the direction of the permitting process.

An Underground Alternative Emerges

Meanwhile, we are learning more about a realistic alternative to NPT’s current proposal that could address some community concerns and provide new public revenues. In November, a state legislative commission released an important report highlighting the feasibility of siting underground high-voltage transmission lines in state-owned transportation corridors. The report can be found here (PDF) and followed a lengthy process of collecting testimony and input from dozens of stakeholders, including CLF and a number of other conservation organizations. The report found that underground transmission technologies and corridors are “being used extensively throughout the U.S. and internationally,” “may increase the reliability and security of the electric transmission system,” and “may be technically and financially competitive with other transmission designs and locations.” The commission pointed to other pending transmission projects that incorporate underground technologies sited in state-owned transportation corridors as an indication that this approach “can be technically and financially viable.” (Earlier this week, New York officials recommended approval of one of these projects – the Champlain Hudson Power Express between Québec and New York City, which now includes more than 120 miles of underground high-voltage transmission in active railroad corridors and highways.)

While the state agency officials participating in the commission were reluctant to endorse specific policy proposals in the report (which they saw as outside the commission’s charge), many commission members emphasized the need for a proactive, comprehensive energy plan and a regulatory framework that would help New Hampshire assure that new transmission projects provide meaningful public benefits.

A majority of the commission’s legislator members recommended changes to the state siting process for energy projects, including a requirement that a transmission developer bring forward an underground alternative to any overhead project. It is expected that these recommendations will be among the many legislative proposals to amend the state siting law during the 2013 session of the New Hampshire legislature.

*             *             *

What will 2013 bring for the Northern Pass project and New Hampshire’s energy future? Stay updated by signing up for our newsletter Northern Pass Wire, and be sure to check in with CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass) and all of our latest Northern Pass posts on CLF Scoop. You can also follow me on Twitter, where I often point to recent news articles on Northern Pass.

Storm Clouds Gather Over Brayton Point

Dec 14, 2012 by  | Bio |  Leave a Comment

Frank C. Grace, www.trigphotography.com

Frank C. Grace, www.trigphotography.com

Coal-fired power is dying, not only across the nation, but across New England as well.  The region’s coal-fired power plant fleet has started to succumb to the costs of operating a coal-fired dinosaur in the age of energy efficiency, growing renewable electricity generation, and–for now–low natural gas prices.

Predominantly coal-fired Brayton Point Station in Somerset, Massachusetts, is the state’s largest single source of carbon emissions (producing over 6 million tons in 2010). Another harmful pollutant emitted by Brayton Point is particulate matter, which is measured daily by monitors that continuously check the opacity of the soot coming out of the plant’s smokestack. Brayton has been violating their limits for emitting that soot, and failing to monitor their emissions of several other harmful pollutants. Yesterday, CLF filed a notice of intent to sue Brayton’s current owners, Dominion Resources, for those violations. CLF’s upcoming lawsuit is just the latest in a growing list of bad news for Dominion and Brayton Point.

As New England’s other coal plants started to close or teeter on the edge of closure, Brayton Point Station was expected to be the last coal plant standing in the region. It is New England’s largest coal-fired power plant, and in the past decade its current owners, Dominion Resources, sank over $1 billion in pollution control upgrades into the behemoth. While Brayton Point does not have the kind of legal protection from market realities that PSNH exploits to prop up its dirty old coal generation in New Hampshire, many had assumed that Brayton Point was well-positioned to survive in the changing power generation landscape.

source: EPA and ISO-NE data

But the relentless pressure of low natural gas prices and the costs of starting up and operating an enormous coal-fired power plant have begun to affect every corner of the coal generation market in New England, and Brayton Point has not been spared. The plant’s “capacity factor,” which reflects the amount of power the plant generated compared to the amount of power it could have generated if used to its full potential, has taken a nosedive over the past three years. A plummeting capacity factor means that it is a better economic choice for a plant’s owners to keep it idle most of the time than to operate.

Dominion Resources, clearly, has seen the writing on the wall for coal in New England. After signing a binding agreement to cease coal operations at Salem Harbor Station as a result of CLF’s lawsuit against that plant, Dominion sold the Salem plant earlier this year. Following closely on the heels of the Salem sale, the company put Brayton Point on the market in September. While Dominion is marketing Brayton as a modern coal-fired power plant due to its recent billion-dollar pollution control investments, UBS recently assessed [PDF] the value of those investments (and the plant itself) at zero.

Brayton Point’s plummeting capacity factor and bleak sale prospects reflect both the current power of low natural gas prices and the weakness of these old, out-dated coal plants.  That trend will continue as the New England energy market continues to move forward with better integration of efficiency, conservation and renewable generation. Dark clouds are rising over Brayton Point. In the meantime, CLF and our partners will work diligently to hold the Brayton Point power plant accountable for producing its own dark clouds of pollution in violation of the law.

An Electricity Supply Tutorial And Maine’s New Green Power Option

Dec 7, 2012 by  | Bio |  3 Comment »

Mainers have recently been seeing and hearing advertisements for alternatives to the standard offer electricity supply that most residential customers receive through their transmission and distribution (T&D) utility. I’ve been ask numerous times to explain the meaning of these new alternatives. This post is written as a guide to that very question.

In Maine, the majority of customers are served by three investor-owned transmission and distribution utilities: Central Maine Power, Bangor Hydro-Electric Company, and Maine Public Service Company. These T&D utilities maintain the transmission lines and related equipment to carry electricity throughout the grid. Prior to 2000, these same utilities also generated electricity.

In 1997, in response to federal changes that decoupled or split generation from transmission, the Maine legislature passed a law requiring that electric utilities divest their generation assets. Additionally, as of March 1, 2000, all Maine consumers had the right to purchase generation service directly from competitive electricity suppliers.

Until recently, however, there have been few options for residential customers other than the standard offer available through each of the T&D utilities. That, thankfully, is changing.

Recently a number of companies have entered the residential electricy supply market in Maine. They operate by purchasing power on the wholesale market, generally at rates slightly lower than the standard offer rate. The electricity itself is primarily generated by conventional power plants.

Another, greener option on the horizon is Maine Green Power. Maine Green Power is currently pre-enrolling customers who wish to offset their energy supply with renewable energy credits generated by 100% Maine-based renewable energy projects. This offer – of entirely renewable energy – is a first for the state, one that is certain to apply pressure on competing providers.

Maine Green Power’s definition of green power projects is, on the whole, in line with CLF policy priorities and includes solar photovoltaic systems; hydroelectric projects that meet state and local fish passage requirements; wind turbines; biomass facilities that use wood, wood waste, landfill gas or agricultural biogas; tidal power projects; geothermal projects; and fuels cells that use landfill gas or agricultural biogas.

To be clear, the power isn’t purchased directly. When power is generated through the above no- or low-emission sources, Renewable Energy Credits (RECs) are created. RECs are then sold by the green power generators to support their further development. These RECs are what Maine Green Power is purchasing and, in turn, what Maine Green Power’s customers are paying for. By doing so, customers are investing in local renewable energy projects, reducing greenhouse gas emissions, and reducing our society’s reliance on fossil fuels.

Let’s put the cost into perspective. A typical Maine household uses roughly 500 kwh of electricity per month. A 500 kwh “block” of renewable energy can be purchased from Maine Green Power for $7.50 per month (a half block of 250 kwh is available for $3.75/mo.). This charge is paid in addition to the standard offer price for electricity.

That, from my perspective, is an entirely reasonable price to pay for a brighter energy future. In fact, when you factor in the currently externalized costs of climate change and dirty energy to our public health, to our environment, and to our economies and communities, I’d say it’s more than a fair deal.

And so, to return to the original question, what exactly do these alternatives mean for the state? They mean a brighter future.

Getting Desperate: Northeast Utilities CEO Falsely Claims Wide Support for Northern Pass

Nov 15, 2012 by  | Bio |  Leave a Comment

This week, the developer of the Northern Pass transmission project, Northeast Utilities (NU), sunk to a new low. In a presentation at a utility industry conference, NU CEO Tom May stated that:

  • “[T]his project has the support of every environmental group in New England basically.”

This is unequivocally untrue. In fact, CLF is not aware of a single New England environmental group that supports the Northern Pass project as proposed. You don’t have to take our word for it: literally dozens of New England’s environmental organizations – regional, state, and local – have registered significant concerns with, or outright opposition to, the proposed project in public comments to the U.S. Department of Energy. May’s statement is all the more puzzling given the energy that NU has devoted to attacking the efforts of groups like CLF (e.g., here and here), the Appalachian Mountain Club (e.g., here), and the Society for the Protection of New Hampshire Forests (e.g., here).

  • The regional electric grid operator, ISO-NE, has been a “big proponent of this project.

This is also inaccurate. Northern Pass is an “elective” transmission project that is not intended to address any electric grid needs identified by ISO-NE. As a result, ISO-NE is obligated to consider the project objectively alongside competing elective projects (of which there are several), and Northern Pass is not specifically endorsed in any of ISO-NE’s planning documents, such as ISO-NE’s recently released 10-year Regional System Plan for the New England electric grid. Because it is an elective project that ISO-NE didn’t ask for and doesn’t plan to rely on, ISO-NE’s primary role in reviewing Northern Pass will be to assure that it won’t have an adverse impact on the reliability of the grid, not to advocate for the project.

  • New Hampshire’s new governor-elect, Maggie Hassan, is “supportive of the project.”

Governor-elect Hassan’s website contains this statement to the contrary:

Maggie opposes the first Northern Pass proposal.  As a state senator, Maggie worked to pass a constitutional amendment to prohibit the use of eminent domain for private gain, and she opposes the use of eminent domain for this project.

Maggie believes that we must protect the scenic views of the North Country, which are vital to our tourism industry.  As Governor, she will ensure that, in accordance with the law, New Hampshire undertakes a rigorous review process of any proposal and provide significant opportunities for public voices to be heard.

Maggie hopes that the next proposal will address the concerns of the communities involved.  She believes that burying the lines would be a more appropriate approach, and also supports looking into home-grown energy sources, such as the new biomass plant under construction in Berlin.

Governor-elect Hassan has also expressed her support for Governor Lynch’s approach to the project: namely, that the directly affected communities must support the project before it moves forward. With almost all the communities on the record opposing the project (and no willingness on the part of Northern Pass’s developer to consider burial as an alternative to overhead lines), it’s impossible to characterize Governor-elect Hassan’s position as support for the project.

(May’s remarks on Northern Pass are at 21:00 – 25:30 in the webcast linked here.)

Since the Northern Pass project was announced more than two years ago, CLF has identified significant problems with the proposal, including the developer’s egregiously misleading marketing of the project’s environmental attributes and other supposed benefits. CLF has repeatedly emphasized, in the words of our President John Kassel, that “long-term supplies of hydro, wind and other sources of power – that respect and significantly benefit the landscape through which they are transmitted, support rather than undermine the development of New England’s own renewable energy resources, replace coal and other dirty fuels, keep the lights on at reasonable cost, and accurately account for their impacts – are what New England needs.” Thus far, the Northern Pass project, as proposed, meets none of these criteria, and therefore is not a project CLF can support.

Beyond our specific concerns, we’ve been fighting for some basic principles that should not be controversial, such as transparency, fairness, and especially honesty. Again and again, NU has unfortunately refused to abide by these principles, repeating discredited claims about the project’s emissions reductions and outdated accounts of other benefits, marginalizing the many stakeholders raising legitimate questions about the project, and employing bullying tactics against project opponents (for the most recent example, see here).

As we explained more than two months ago, Northern Pass still has no clear path forward. In concocting a story of broad-based political and stakeholder support, NU is – deliberately or recklessly – misleading its investors with plainly false information: an unacceptable breach of NU’s legal obligations as a public company and of investors’ trust. It is incumbent upon NU to correct the record immediately and to jettison its aggressively deceptive approach to securing approval of the Northern Pass project. The public deserves far, far better.

Change is Hard, Necessary: Rethinking Our Electricity System Post-Sandy

Nov 1, 2012 by  | Bio |  2 Comment »

Change is hard.

And the larger, more important and more entrenched the thing being changed, the harder it is.

There are few things that are larger and more important than our electricity system. Just ask a parent of a child who was in the intensive care unit of a New York City hospital when Hurricane Sandy wiped away the electric grid and the emergency generators failed. In some moments, like that, electricity is quite literally a life-saver.

In 1882, the world’s first practical coal fired electric power plant came online in New York. For the last fifty years coal has been the dominant fuel and backbone of our electric generation system, spawning a  massive industrial process of extracting coal from the earth, transporting it to power plants, burning it to make heat, transforming it into electricity, and finally disposing of the plants’ waste products into the air, land and water.

Given coal’s longstanding role in maintaining a stable electricity system in this country, it is not shocking that some reasonable folks find it hard to contemplate life without it – despite the evidence of the harm it causes both to human health and the environment.

But ending our dependence on the most harmful fuels to generate electricity is part of the change we need to make if we are going to avert full-on climate disaster. The hard truth is that past emissions of greenhouse gas pollution from coal plants and other dirty fuel sources have already transformed our world, warming our oceans and increasing the water vapor in our atmosphere. As a result, the weather dice are now loaded in favor of catastrophes like Hurricane Sandy, among many other effects.

Propping up and retaining our obsolete and inefficient old coal plants so they can continue to spew global warming greenhouse gases into the air is not an option – and thankfully, the economic tide in this country is starting to turn against them. But after decades of depending on coal for electricity, many wonder how we are going to keep the lights on without it. The answer, to borrow a phrase, is: “Use less electricity, mostly renewable.”

The first step is very clear: we must be much smarter and careful about how we use electricity. This means going all out in our deployment of  energy efficiency that slashes energy use at all times, and also reducing electricity demand at the moments of greatest need when the system is pressed hardest. We are evolving towards a world where highly flexible demand will simply be a routine part of our energy system – our dishwashers, cell phone chargers and air conditioners will ramp up or down their energy use based on price signals and energy system conditions.

Second, we need to redouble our commitment to develop zero emissions renewable electricity generation like wind and solar. Every watt of energy we get from those sources displaces the need for energy that comes from the burning of fossil fuels. Eventually, we will be able to store enough of that clean power to meet demand even when the wind isn’t blowing or the sun isn’t shining. But, until that technology matures, we will still require some “firming” power to fill in the gaps.

Here in the Northeast, that power is likely to come from sources like hydroelectric dams, or natural gas fired power plants, which are cleaner and cheaper than coal, but  come with their own environmental price tags. The specter of over-dependence on natural gas is the cause of much consternation in environmental and energy expert circles. And for good reason: locking ourselves into dependence on a finite imported fossil fuel would be a mistake. Instead, we need to carefully manage our transition to a new and cleaner power system, ensuring that we maintain a sufficiently diverse portfolio of resources and keep the lights on as we move surely and steadily away from fossil fuels.

The transition from dependence on coal to natural gas in our electricity system is crudely analogous to a heroin addict moving to methadone. It is a step in the right direction and movement away from a dangerous addiction, but it is still only a partial step toward toward the full recovery we need: elimination of greenhouse gas pollution from our electric system.

Fundamental change is indeed hard, but the roaring winds of Katrina, Irene and Sandy loudly remind us that we have an absolute obligation to step up and manage the transition to a better, safer and cleaner energy future.

Update: Support Grows for CLF’s Fight to Secure a Fair Review of Northern Pass

Oct 25, 2012 by  | Bio |  Leave a Comment

Members of NH's Congressional delegation are demanding that DOE Secretary Steven Chu (pictured) explain DOE's process for selecting the current contractor team working on the Northern Pass envrionmental review.

Two weeks ago, CLF exposed and brought to the public’s attention internal government documents showing that the Department of Energy (DOE) has illegally allowed the developer of the Northern Pass transmission project, Northern Pass Transmission LLC (NPT) to have significant and improper influence over the ongoing permitting process and environmental review of the project. After filing its concerns about the information with DOE, CLF issued a call to action, urging the public to join CLF in demanding that DOE replace the contractor team charged with preparing the crucial Environmental Impact Statement (EIS), which was handpicked by NPT, with a new, unbiased contractor or internal team with no conflict of interest.

We’re pleased to report that the responses – your responses – to the revelations and our call to action has been remarkable.

In the past two weeks, more than 300 members of the public (and counting) filed comments with DOE demanding replacement of the contractor team and a new commitment to a fair and open permitting process for Northern Pass. (You can take action yourself and file your own comment via this link.)

Yesterday, in a joint letter to DOE, a group of nine organizations representing New Hampshire’s conservation community and the grassroots opposition to Northern Pass, along with more than 60 individuals, expressed their deep concerns about the information exposed by CLF and called for a new EIS contractor with no conflict of interest. (Coverage on NHPR here.)

In the past week, Senator Jeanne Shaheen, Senator Kelly Ayotte, and Congressman Charlie Bass have each sent letters to DOE Secretary Steven Chu demanding that the matter be reviewed and addressed immediately. (Union Leader coverage here.)

  • In her letter to Secretary Chu, Senator Jeanne Shaheen demands an “immediate, detailed response” from DOE to determine whether a conflict of interest exists, emphasizing that “in order for the public to have confidence in DOE and the outcome of any Presidential Permit application there can be no conflict of interest or appearance of conflict in the application process” and that “[a] loss of faith from stakeholders would be difficult, if not impossible, to restore. “
  • Senator Ayotte’s letter urges DOE to review CLF’s concerns and highlighted the need to “make certain that the outcome of this process is perceived as legitimate and that the process remains transparent.”
  • Congressman Bass is asking for a “detailed explanation of the DOE selection of the EIS contractor” in light of “the importance of this matter to the state of New Hampshire and the absolute necessity for a fair and transparent process for all stakeholders.”

It’s clear that the documents CLF disclosed provide only the part of the story of DOE’s mishandled process so far – we don’t know exactly what DOE did internally, in phone calls with NPT and others, or in closed-door in-person meetings. That’s why the members of the delegation are right that DOE owes them and the public a detailed explanation of what happened.

Since CLF’s detailed filing with DOE, we’ve actually learned more about the process from NPT than from DOE. In a letter sent to DOE last week, NPT admitted – rather than rebutted – the facts CLF has exposed. NPT admits that DOE directed it to conduct the contractor search, including the vetting of potential contractors for conflicts of interest .  NPT also admits that it – not DOE – drafted several key documents governing the environmental review and DOE’s arrangement with the contractor team. In effect, NPT admits its enormous, behind-the-scenes role and still can’t understand why anyone would have a problem with it. (We previously explained why NPT’s and DOE’s defensive responses to this effect were off the mark.)

NPT’s letter also publicly disclosed a crucial part of the story for the first time. According to a footnote in the letter, NPT was permitted to “rule out” the qualified environmental review teams at DOE’s own National Laboratories because their rates were higher than NPT wanted to pay. The fact that DOE deferred to NPT’s desire to keep down the costs of the federal environmental review of Northern Pass (even as it spends many multiples of market value to acquire properties in Coos County for the northernmost corridor for the project) is among the most troubling information we’ve yet obtained: if true, DOE did not even consider hiring its own experts to prepare the EIS. It’s hard to imagine clearer evidence that the contractor selection process violated the federal regulations requiring that that the choice be “solely” DOE’s or that the violation directly threatens the integrity and rigor of the environmental review.

Above all, the public’s responses to the revelations about NPT’s role in the DOE permitting process make crystal clear that New Hampshire deserves – and is insisting on – a truly fair, rigorous, and objective review of the Northern Pass project, not the deeply mishandled, applicant-driven process we’ve seen to date.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.

DOE and NPT Don’t Get It: the Public Deserves an Unbiased Review of Northern Pass

Oct 12, 2012 by  | Bio |  1 Comment »

Yesterday, the U.S. Department of Energy (DOE) and Northern Pass Transmission LLC (NPT) reacted in the media (here and here) to news stories reporting that the federal review of the Northern Pass project has been tainted by DOE’s abdication of critical responsibilities to the project developer and permit applicant, NPT. It is frustrating, but not unexpected given what the document trail revealed, that DOE and NPT don’t see any problems with the permitting process to date.

DOE says that it exercised independent judgment in selecting the contractor team and considered other contractors for the job (while it won’t say which ones or how many, apparently absent a FOIA request, which – if CLF’s last request is an indication – could take as long as a year).

While it is clear DOE signed off on the new team, DOE is ignoring that its actions were wrong because of the undisputedly pervasive role DOE allowed NPT to play –with NPT’s counsel personally recruiting, assembling, and coaching the team, helping the team make its proposal to DOE, making a side agreement (of which DOE apparently has no copy) with the team setting the budget and schedule for the process, and actively helping to draft key DOE documents governing the environmental review.

Giving NPT this role and opportunity for influence is at odds with the core purpose of the legal requirement that any third-party contractor be chosen solely by DOE without meaningful participation by the permit applicant: the selected contractor must have no conflict of interest in favor of the applicant – even a perceived conflict of interest. Like DOE itself, the contractor must be seen by the public as an impartial, independent arbiter of the data, the facts, and the analysis contained in the environmental impact statement of the project. Here, the public can have no confidence that this will be true precisely because NPT was so instrumental in choosing the contractor team. The documents make clear that the contractor team owes its job to NPT. How can the public have any confidence that the team will fulfill its obligations indepedently, with no special treatment or preferences for NPT?

DOE’s other comment – that it is routine for applicants to be involved in selecting contractors – is merely an admission that DOE always handles permitting processes in unacceptably close coordination with developers. “We always do it this way,” is no excuse for illegal and improper conduct.

Indeed, it is telling that DOE has no comment on evidence of actual bias on the part of a senior member of the contractor team who – even before being hired – stated the position (one favored by NPT) that the Champlain-Hudson transmission project is not an alternative to be considered as part of the Northern Pass alternatives review. This evidence means that there is not only a risk of bias with the current contractor team, but that bias already has crept into the process – and on a critically important aspect of the environmental review.

By just adding CLF’s filing (PDF) to the pile of public comments received on the project to date, DOE appears to be following a strategy of bureaucratic defensiveness and imperviousness to public feedback – a strategy that is reflected in one of the most troubling documents CLF obtained, an internal email revealing that one of DOE’s principal priorities is to avoid “setting the precedent of backing down under the weight of public criticism.” If DOE continues on this path, as we say in our filing, “it would be fair for the public to conclude that DOE is not interested in meaningful public involvement and is incapable of reaching a legitimate final decision on the permitting applications that the President and Congress have entrusted it with faithfully reviewing on the nation’s behalf.”

For its part, NPT’s response reflects the absurd allegation that CLF merely is trying to cause delay. To the contrary, our filing with DOE implores the agency to fix the process now, before the permitting process begins again in earnest. Given that there are still several months before NPT says it will restart the process by filing a new northernmost route for the project, DOE has ample opportunity to cure deficiencies.    To be clear, every day of delay that has occurred to date is NPT’s doing – DOE has allowed NPT to drag out the federal environmental review for two years so that it can assemble a new northernmost route, without a definitive end in sight.

NPT also says CLF is trying to “preemptively discredit” the process. Of course, it isn’t CLF’s filing but instead DOE’s and NPT’s own actions, documented in black and white in the 22 exhibits to our filing, that are preemptively discrediting the process.

You can help CLF tell DOE – in only a few clicks – that its actions are unacceptable and that New Hampshire deserves a truly fair review of Northern Pass. Please take action now.

To learn more about this issue, take a moment to review our posts from earlier this week here and here.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.

Its Objectivity and Integrity Again in Question, the Federal Review of Northern Pass Comes to a New Crossroads

Oct 11, 2012 by  | Bio |  Leave a Comment

(photo credit: flickr/timtom.ch)

The new revelations of unfairness and bias in the federal environmental review of Northern Pass have struck a chord, garnering front-page coverage in the Union Leader and a story on New Hampshire Public Radio. You can join our fight for a fair review of Northern Pass. We have made it easy for you to take action and tell the United States Department of Energy (DOE) that New Hampshire deserves an unbiased process that follows the law – it will only take a couple of seconds. You can submit your comment to DOE here.

To understand what’s at stake in the wake of these developments, it’s important to take a look back at the history of where we’ve been and what we’ve been fighting for.

This week marks the second anniversary of the formal announcement of the Northern Pass project and Northern Pass Transmission LLC’s (NPT) application to DOE for a Presidential Permit. Shortly after the announcement, it became clear that DOE’s review of the project was off to a terrible start. DOE had selected a “third-party” contractor to prepare an environmental impact statement or “EIS” for the project – a crucial, comprehensive, and impartial study of the project’s environmental and socioeconomic impacts and its reasonable alternatives. But that contractor, Normandeau Associates, was the same firm that was on NPT’s payroll to advocate for the project’s approval during the state siting process, which will follow the federal process. This was a clear conflict of interest in violation of the regulations that govern federal environmental reviews.

After CLF and others objected to DOE’s hiring of Normandeau on the ground that the contractor had, NPT initially defended Normandeau’s dual role. Then, in an about-face, NPT terminated the arrangement, saying that:

[T]he strong expressions of concern by certain members of the public about the arrangement lead us to believe that continuing with this arrangement may cause the public to lack confidence in the objectivity and rigor of the ultimate environmental analysis of the project. That outcome obviously does not serve the interests of the project, any of the permitting agencies or the public.

It turns out, however, that our fight for fairness and integrity in the Northern Pass permitting process was only beginning. Over the last two years, CLF has advocated for a truly rigorous analysis of alternative technologies and strategies, a comprehensive review of the region’s energy needs, and a much more honest accounting of the current proposal’s impacts – on electric bills, the climate, our domestic renewable power industry, and natural resources in Canada – than the threadbare and misleading information NPT has provided to DOE and to the public. Along the way, CLF has encouraged members of the public to make themselves heard in the permitting process and sought improvements in that process.

After DOE announced it had selected a new, supposedly independent contractor team to prepare the EIS, CLF identified the potential for unfairness in DOE’s agreement with the contractor and encouraged DOE to fix the problems. We’ve been joined in this important fight by many, many other advocates, from the record crowds at DOE’s public meetings in March 2011, to passionate Granite-Staters on and off the project’s path, to our allies at other environmental organizations.

What we’ve now learned – that DOE has repeatedly abdicated its responsibility to control the process and that NPT has had improper influence over major decisions about the review – has deeply shaken our confidence in the process we’ve been fighting so hard to protect and improve. With NPT expected to announce a new northernmost route soon (now the end of 2012) and restart DOE’s review once again, we are at a new crossroads, just as we were at the process’s outset. Will the federal review of Northern Pass be the fair, objective, and open process that New Hampshire deserves? Or is the game rigged in the developer’s favor yet again?