Ratepayers Subsidizing PSNH’s Addiction to Coal

Jun 4, 2012 by  | Bio |  Leave a Comment

This Sunday, an Op-ed of mine appeared in The Portsmouth Herald. Below find a copy of the original text. You can find a copy of the original story here.

The nation and New Hampshire are relying less and less on coal — our dirtiest, least efficient fuel — to meet our electric power needs. PSNH recently announced it is not operating its flagship coal plant, Merrimack Station in Bow; the plant will sit completely idle for six months of 2012. The two coal boilers at PSNH’s Schiller Station in Portsmouth will operate even less. Yet, PSNH customers continue to pay a premium to keep PSNH’s coal plants on life support, thanks to a regulatory system that protects PSNH’s interests over those of ratepayers.

Coal-fired power plants — expensive new facilities and decades-old dinosaurs like PSNH’s plants alike — can’t compete in today’s marketplace. Investors and customers are moving toward cleaner, cheaper alternatives, principally natural gas, but also renewables (especially wind) and high-tech ways of reducing energy use. Northeast Utilities — PSNH’s parent company — admits that this reality is not going away anytime soon.

Indeed, the trend is accelerating. In the first quarter of 2012, coal power accounted for only 36 percent of the nation’s total electric output — the smallest role for coal in a generation and down almost 9 percent from the first quarter of 2011. Regionally, a new milestone came in April, when the New England regional electric grid operator announced that, during the previous month, the entire New England coal fleet was uneconomic — meaning there was not a single hour when a coal plant was able to compete with other energy sources. Despite coal’s downward trajectory, PSNH made big bets that the market for coal-fired power will exist for years to come. Exhibit A: PSNH’s investment — over vigorous opposition from the Conservation Law Foundation, ratepayer advocates and others — in a $422 million life extension project for Merrimack Station. If PSNH gets its way, ratepayers will foot the whole bill, plus a 10 percent guaranteed profit for PSNH’s sole shareholder, Northeast Utilities.

Why has PSNH been so richly rewarded for bad economic decisions? Put simply, New Hampshire’s relic of a regulatory system still protects PSNH and its coal plants from the market. Remarkably, ratepayers continue to pay for upkeep and staffing at PSNH power plants, even when they sit idle, and also pay that same 10 percent profit on the book value of all PSNH assets. No other power plant owner in New England gets such special treatment. Yet PSNH continues to sidestep scrutiny.

Earlier this year, following a massive lobbying effort orchestrated by PSNH, the New Hampshire House voted to table a bill that would have forced a hard look at PSNH’s continued ownership of these obsolete power plants.

In the meantime, PSNH remains in an economic “death spiral” with few large business customers to cover its costs and its remaining customers — homeowners and small businesses — now paying as much as 50 percent more for power than customers of other utilities, which get their power from the competitive market. Under the status quo, PSNH will siphon more than a $100 million in above-market costs out of the New Hampshire economy this year.

For the environment, the climate, and the long-term public and fiscal health of the communities surrounding these plants, coal’s demise is encouraging news. The market is providing an unprecedented opportunity to relegate coal power to the history books for good. New Hampshire should seize it.

The “New Route” for Northern Pass Won’t Cure Its Failings

May 24, 2012 by  | Bio |  Leave a Comment

This summer, New Hampshire is bracing for news of the Northern Pass project’s future and its “new route.”

It’s now been nearly a year since the federal permitting process for the Northern Pass project was put on indefinite hold. North of Groveton, New Hampshire, the developer – Northern Pass Transmission LLC (NPT) – is still working behind tightly closed doors to string together a new section of the project route, where there are no existing transmission corridors, by paying landowners substantial sums for property – in many cases, well above market value.

Earlier this month, the chief operating officer of NPT’s parent company, Northeast Utilities, told investors:

Where we are right now is in procuring the last 40 miles of the right-of-way, and I can tell you we are making very, very strong progress in lining up the right of way. I think we’re on track for the middle of the year, approximately August timeframe to have the right-of-way secured and then to be prepared to file with the [U.S. Department of Energy] the route….

NPT’s apparent plan (assuming it really can overcome the considerable obstacles to a new route):

Not so fast. Before the news arrives (if it does), it’s worth remembering that whatever new lines the developer manages to draw on the map do nothing to change the project’s DNA or to demonstrate that the project will benefit New Hampshire. A brief review is in order:

Where are the benefits for New Hampshire?

Through  costly marketing efforts, NPT has been trying to sell New Hampshire on the tremendous economic and environmental benefits of Northern Pass. But the supposed benefits just don’t hold up to scrutiny:

  • Reduced emissions from “clean power”?

In terms of greenhouse gas emissions, CLF’s report on the most recent science demonstrated that new hydropower projects to supply power for Northern Pass are much worse for the climate than NPT’s false advertising claims have led the region to believe and are not meaningfully better than natural gas power plants (the power NPT predicts that Northern Pass would replace) in the early years after reservoirs are developed. As a result, contrary to mistaken but widely disseminated assumptions, importing hydropower from Canada is not a short-term solution that will reduce New England’s or New Hampshire’s carbon emissions. Indeed, the current proposal would have the perverse effect of protecting – rather than hastening the transition away from – PSNH’s low-performing, high-emitting power plants, which are New Hampshire’s largest source of greenhouse gas emissions. (Despite marketing the project based on its “clean” source of the power, NPT also refuses to acknowledge the relevance or importance of the troubling damage to ecosystems and communities that large-scale hydropower causes in Canada.)

  • Lower electric rates?

Those who would live with the new transmission lines, customers of NPT affiliate PSNH, are the least likely to benefit. Despite nearly two years of promises that PSNH would announce a plan to purchase Hydro-Québec hydropower for New Hampshire residents, there is still no agreement to do so. Any modest effects on the region’s wholesale electricity rates (which NPT’s consultant predicted based on outdated economic assumptions about energy costs) don’t translate into lower rates for PSNH customers (who instead are stuck paying the bill for PSNH’s inefficient and dirty power plants). In fact, if Northern Pass succeeds in lowering wholesale rates, it will likely worsen PSNH’s death spiral of increasing rates and fewer customers, leaving those residents and small businesses still getting power from PSNH with higher bills.

  • Growing New Hampshire’s clean energy economy and jobs?

There is a substantial risk that Northern Pass would swamp the market for renewable energy projects in New England, especially if state laws are amended to qualify Hydro-Québec power as “renewable.” Furthermore, the project’s high voltage direct current technology means that its massive investment in transmission capacity will wholly bypass the potentially fertile ground for renewable energy development in northern New England. Whatever the short-term construction jobs required (and NPT’s estimates are disputed), the current Northern Pass proposal may diminish the prospects for New Hampshire’s clean energy economy, including needed permanent jobs in the renewable and energy efficiency sectors.

No regional plan addressing new imports

Québec continues to implement its ambitious plan to develop more wild Boreal rivers into a new generation of massive hydropower projects, which will increase its export capabilities. This January, Hydro-Québec commissioned the final turbine at its latest hydropower facility (Eastmain 1-A) and will commission other turbines (at Sarcelle) as part of the same overall project later this year. Construction at the $8 billion Romaine River hydropower project (the subject of the film Seeking the Current) has begun and is ongoing, with the first unit expected to come online in 2014. Northeast Utilities has affirmed that Northern Pass will tap the power from these new projects. Meanwhile, Northern Pass competitors are moving forward with new transmission projects in eastern New England and in New York, among others:

Northern Pass and competitor transmission projects (source: ISO-NE)

More than a year ago, CLF and others urged the Department of Energy to weigh the region’s energy needs and develop a strategic regional plan that would determine a well-informed role for new Canadian hydropower imports in the northeastern United States’ energy future – before moving forward with the permitting process for Northern Pass. NPT’s only response was that responsible planning – encompassing the other pending transmission projects and a full consideration of the reasonable alternatives – would unacceptably delay its project – a truly ironic claim given NPT’s own, unforced, ongoing delay. More incredibly, the Department of Energy has so far sided with NPT, without explaining why.

So as Québec builds more dams and NPT buys up land, our region has no plan of its own. With no framework to understand the nature and extent of the appropriate role for Canadian hydropower, it is difficult if not impossible to make a sound, well-informed decision on whether Northern Pass – or projects like it – should proceed.

Community and grassroots reaction throughout New Hampshire

Since Northern Pass was announced in 2010, the project has inspired a broad-based and spirited movement of people throughout New Hampshire to oppose the current proposal. Last spring, there were massive turnouts at the Department of Energy’s public hearings on the project, with literally thousands attending and providing written and verbal comments both questioning the merits of the current proposal and urging a thorough environmental review. And earlier this year, a coalition of citizens and organizations of many political stripes succeeded in persuading New Hampshire’s legislature to enact a bill preventing projects like Northern Pass from using eminent domain. In another effort, more than 1,500 donors contributed total of $850,000 to enable the Society for the Protection of New Hampshire Forests to preserve the treasured New Hampshire landscape surrounding the historic Balsams resort, including a parcel that NPT had sought to purchase as part of Northern Pass’s transmission corridor. To date, town meeting voters in 32 local communities have passed resolutions and ordinances against the current proposal. Critically, most of these communities are located along the NPT’s “preferred route” that follows PSNH ‘s existing transmission corridor, south of any “new route” that NPT may announce.

NPT’s refusal to consider routing and technological alternatives

At every turn, NPT has rejected calls for in-depth consideration of potential alternatives to its current proposal, including use of an existing high-voltage transmission corridor that extends from Canada, through Vermont and western New Hampshire, to Massachusetts; burying transmission lines in transportation corridors, as is proposed in the New York and eastern New England projects mentioned above; or adding capacity to that same New York project, consistent with that project’s original proposal (it has since been scaled back). Indeed, Northern Pass’s response to the public’s opposition to the project was to “withdraw support” for alternative routes and double down on its “preferred route.” While this stance may be in the economic interest of NPT and PSNH, it’s grossly at odds with a fair, well-informed permitting process that would vindicate the public’s interest in a solution with minimal environmental and community impacts.

If and when NPT comes back from its year of buying up North Country land and relaunches its effort to secure approval of the Northern Pass project, with the only change to the proposal consisting of a new line on the map north of Groveton, there should be no mistake: the fundamental flaws in the current proposal remain. Likewise, whatever NPT’s “preferred route,” CLF remains as committed as ever to securing a comprehensive and rigorous permitting process that identifies superior alternatives and a final outcome that moves us toward – and not away from – a clean energy future for New Hampshire and the region.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.

The Writing Is on the Wall for Coal. Will New Hampshire Notice?

May 10, 2012 by  | Bio |  1 Comment »

We are in the midst of a massive, historic retreat in the nation’s use of coal to produce electricity, which began in 2008. This ongoing shift away from our dirtiest fuel has made news around the country. The primary reason: coal-fired power plants – expensive new facilities and decades-old dinosaurs alike – can’t compete in today’s marketplace. Investors and customers are moving toward cleaner, cheaper alternatives, principally natural gas but also renewables (especially wind) and high-tech ways of reducing energy use.

The national trend is occurring here in New Hampshire and throughout New England. This week, New Hampshire learned that PSNH is not operating its flagship coal plant, Merrimack Station in Bow, and that its economic prospects are not good. In fact, the plant will sit completely idle for six months of 2012, prompting the Manchester Union Leader to run the headline, “PSNH’s Bow power plant shuts down.” (The word “temporarily” was later added to the online story.) The two coal boilers at PSNH’s Schiller Station in Portsmouth will operate even less. (The Nashua Telegraph also took note.) This is welcome and long overdue relief for New Hampshire from New England’s top toxic polluter, and it would not have happened without legal pressure from CLF and others. More on our work in a moment.

Across the region, coal use has been collapsing for some time — and this was not unpredicted, as PSNH is claiming. PSNH’s claims to the contrary convey its willfully myopic planning perspective – a direct result of its expectation that ratepayers will cover its costs with a handsome profit irrespective of how utterly unsuccessful its investment decisions have been.

Coal-fired power plants’ “capacity factors” – their actual power output as a percentage of their theoretical maximum output at full power, running 24/7 – are intended to be very high; these plants were designed to run at close to full power day and night as “baseload” power for the electric grid. Not anymore:

In 2012, the trend is accelerating. Nationally, the U.S. Energy Information Administration reports that, in the first quarter, coal power accounted for only 36% of total generation – the smallest role for coal in a generation and down almost 9% from the first quarter of 2011. Regionally, a new milestone came in April, when the regional electric grid announced that, during the previous month, it didn’t dispatch any power from New England coal plants to meet the region’s electric demand.

For public health, air quality, the environment, the climate, and the communities where these plants are located, these trend lines are all in the right direction. For years, CLF’s Coal-Free New England 2020 campaign has fought to speed this progress and to make it permanent, by holding plant operators accountable for violating environmental laws (including at Merrimack Station), securing final and binding agreements to guarantee closure, and working in coalition with local residents to plan for responsible redevelopment and reuse of the plants’ sites.

In New Hampshire, with the complicity of state regulators, PSNH made big bets that the market for its coal-fired power will exist for years to come. One such spectacularly bad gamble was PSNH’s investment – over vigorous opposition from CLF, ratepayer advocates, and others – in a life extension project for Merrimack Station, including air pollution controls that address only some of the plant’s toxic and harmful emissions, to the tune of $422 million, plus a 10% guaranteed profit, money it now wants back from New Hampshire residents and small businesses through the regulator-approved rates it charges. Given coal’s collapse, which CLF and ratepayer advocates predicted at the time, this investment looks absurd and unwise, except of course to PSNH and its parent company Northeast Utilities, which has repeatedly reassured shareholders it is entitled to get back the full value of the upgrade, even if the plant barely runs.

Why has PSNH been so richly rewarded for such terrible economic decisions? Put simply, New Hampshire’s backward relic of a regulatory system is still protecting PSNH and its coal plants from the market. Remarkably, ratepayers continue to pay for upkeep and staffing at PSNH’s power plants, even when they sit idle, and also pay that same 10% profit on the value of all PSNH assets, including its quiet coal piles – and that’s whatever book value PSNH assigns, not market value.

PSNH has fought tooth and nail to protect its special treatment. Earlier this year, PSNH pulled out all the stops to kill a bill that would have directed state regulators to investigate whether PSNH’s ownership of power plants, including Merrimack and Schiller Stations, is in the best interest of ratepayers. After PSNH’s full-court press of lobbying, editorial board visits, and pressure from PSNH employees as well as PSNH-allied unions, politicians, and chambers of commerce, the House tabled the bill.

In the meantime, PSNH remains in an economic “death spiral” with very few large business customers to cover its costs. As a result, its remaining customers – homeowners and small businesses – are now paying as much as 50% more for power (8.75 cents per kilowatt-hour) than are customers of other utilities – which do not own power plants and get all their power from the competitive market (around 6 cents per kilowatt-hour). And the Legislature continues to seek the rollback of New Hampshire clean energy laws under the guise of easing ratepayer burdens, mistaking small trees for the forest of PSNH’s above-market rates, which include the costs of both PSNH’s idle fleet and buying power from more efficient plants.

What is CLF doing about it? Against the odds, we’re succeeding at forcing New Hampshire regulators to scrutinize PSNH’s costs, and the fact that PSNH’s coal plants are now sitting idle and the corresponding benefits to public health and the climate are a product of that scrutiny and a testament to CLF’s advocacy. And we’re pushing for regulators to do much more to hold PSNH accountable for its abysmal planning and force PSNH’s shareholder Northeast Utilities – and not suffering PSNH ratepayers, who are paying among the nation’s highest electric rates – to bear the downside of PSNH’s bad bets on coal. The last thing we should be doing with our energy dollars is subsidizing dirty power that can’t compete.

The market is providing an unprecedented opportunity to make that Union Leader headline from this week – and headlines like it for every other coal plant in the region – an enduring reality as New England transitions to a clean energy future. New Hampshire and the rest of New England should seize it.

A dispatch from the future? Manchester Union Leader headline, May 8, 2012

Massachusetts Can’t Rely on the Northern Pass Proposal as a Short-Term Climate Solution

May 4, 2012 by  | Bio |  Leave a Comment

Amid new scrutiny, it’s time for Massachusetts to reckon with the elephant in its climate plan (photo credit: flickr/David Blackwell)

The 5 million ton elephant in Massachusetts’s nation-leading climate action plan – the oversold and overstated greenhouse gas emissions reductions from new imports of Canadian hydropower comprising more than 20% of the state’s goal – is too big to ignore. That’s why it’s encouraging that the plan’s misplaced reliance on the Northern Pass transmission project is receiving new scrutiny.

Last December, CLF identified a significant problem with Massachusetts’s “Clean Energy and Climate Plan for 2020”: it adopted and relied on Northern Pass’s sales pitch that the project will reduce carbon dioxide emissions by 5 million tons annually and then claimed all those emissions reductions for Massachusetts. After examining the basis for the 5 million ton figure, we concluded that – no way around it – the figure was just wrong; it was calculated on the false assumption – belied by Hydro-Québec’s own data – that imported hydropower has no greenhouse gas emissions.  The way Massachusetts was relying on Northern Pass was dubious for other reasons, including the unfairness of Massachusetts claiming all the benefits of a project that will not be located in the state and the fact that there is no concrete commitment regarding how much Northern Pass power Massachusetts electric customers will actually receive.

In February, the problem was confirmed in a technical report (PDF) commissioned by CLF and authored by Synapse Energy Economics, which found that hydropower facilities, especially new projects being built in Québec to supply new imports into New England, have substantial greenhouse emissions – emissions that for several years after construction can be comparable to the natural gas power that Northern Pass would replace.

Last month, Massachusetts think-tank MassINC released an independent analysis (PDF) of Massachusetts’s progress in meeting its ambitious emissions reduction goal – 25% below 1990 levels by the year 2020. The conclusion: Massachusetts is making great strides in some areas, but needs to redouble its efforts if it intends to achieve the goal. One of the biggest uncertainties: the Massachusetts climate plan’s reliance on new imports of Canadian hydropower through Northern Pass.

MassINC’s new report signals, as CLF has argued, that Massachusetts must look elsewhere to secure sufficient emissions reductions by 2020. The MassINC report makes the critical point that it is not up to Massachusetts whether the Northern Pass project is built – and there are many reasons to doubt that it ever will be – not the least of which are the extensive permitting processes and the committed and well-founded community opposition that the project must overcome. Citing Synapse’s findings on the greenhouse gas emissions of hydropower and the higher emissions associated with new hydropower facilities, the MassINC report suggests that any reliance on new imports as an emissions reduction strategy requires a credible, scientifically sound accounting of the targeted reductions, including whether and to what extent the power will come from new hydropower projects. Massachusetts needs to temper its enthusiasm for additional hydropower imports with the same scientific rigor and attention to detail reflected in the Patrick administration’s proposed regulations for biomass power.

The MassINC report is making waves, earning the lead, front page story recently in the Boston Sunday Globe and media coverage throughout the state. Consistent with the MassINC report, CLF does not rule out the possibility that new hydropower imports – if they have minimal environmental and community impacts on both sides of the border, avoid undermining local renewable and energy efficiency, displace our dirtiest power, and provide verifiable emissions reductions – could play a constructive role in a cleaner energy future for the region, particularly when considered over the long term.

But it’s time for the Patrick administration to reconsider its unfounded confidence that Northern Pass is some kind of clean energy panacea that will deliver a fifth of all needed emissions reductions by 2020. The science is clear: it’s not.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.

Northern Pass Developers Refuse to Face Facts about Hydropower Emissions

Apr 4, 2012 by  | Bio |  Leave a Comment

The American developers of the Northern Pass project are misleading the public about the project’s most touted environmental benefit (without which they “wouldn’t be doing this”): reducing New England’s greenhouse gas emissions. Presented with clear, unambiguous evidence that the current proposal would not meaningfully reduce emissions and that their public relations campaign is trading in falsehoods, the developers have done nothing to correct the record or provided any substantive response to the evidence.

In mid-February, CLF released a report on the science regarding large-scale hydropower’s emissions of greenhouse gases, the pollutants that are driving climate change. The conclusion: large-scale hydropower projects, especially new facilities, have substantial greenhouse gas emissions that, in their first years of operation, are equivalent to emissions from modern natural gas power plants.

This conclusion means that the proposed Northern Pass project, which would import up to 1,200 megawatts of new Canadian hydropower into New England and displace power from domestic natural gas plants, would not meaningfully reduce greenhouse gas emissions, as the developers are claiming.  CLF’s report also demonstrated that the assumption at the heart of the developers’ claim that the Northern Pass project would reduce emissions by 5 million tons per year – that Canadian hydropower has no greenhouse gas emissions – is unequivocally false.

CLF sent a copy of the hydropower emissions report to Northern Pass Transmission LLC (NPT). In our transmittal letter, we made clear that the science summarized in the report (some of which was included in NPT’s own regulatory filings) clearly contradicted NPT’s marketing claims and urged NPT to:

  • correct the regulatory and public record by retracting and withdrawing all NPT prior statements that hydropower results in no emissions of greenhouse gases and that the Project will reduce carbon dioxide emissions by any specific amount, and
  • refrain from making any claims regarding carbon dioxide emissions reductions associated with the Project unless and until those reductions are substantiated in a new technical analysis subject to public and permitting agency review.

To date, NPT has taken neither step. The false “no emissions” canard and the unsupported claim of 5 million tons of annual emissions reductions from the project are still prominent fixtures at NPT’s MyNewHampshire.com:

"No greenhouse gases" (source: http://www.northernpass.us/pdf/ads/Jack.pdf)

NPT spokesman Martin Murray did post a non-responsive comment on CLF’s website, to which I responded in detail here. On its own website, NPT then heralded a Hydro-Québec press release responding to the report, and I explained here why the press release neither reflected a close reading of the report nor challenged the report’s fundamental conclusions but, instead, underscored Hydro-Québec’s position that the major promise of new hydropower imports was as a long-term replacement for dirty, costly coal power plants like New Hampshire’s own Merrimack and Schiller Stations – not natural gas.

Where do NPT’s non-responses leave us? Unfortunately, NPT seems poised to continue on with its false and misleading public relations campaign and has shown no interest in an open, honest debate. CLF will continue to use all the tools at our disposal to ensure that the public and decision-makers are fully aware of all the issues associated with the Northern Pass proposal. 

You can support our work by becoming a CLF member and also by telling the permitting agency now reviewing the Northern Pass proposal to consider hydropower’s greenhouse gas emissions – and all the other impacts of Northern Pass power in Canada – as part of the agency’s environmental review – click here to take action.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass), and take a look at our prior Northern Pass posts on CLF Scoop.

ACTION ALERT: Tell the Department of Energy – Consider the Impacts of Northern Pass Hydropower!

Mar 23, 2012 by  | Bio |  1 Comment »

Seeking the Current filmmaker Nicolas Boisclair on the bank of Québec's Romaine River (photo courtesy Chercher le Courant)

This month, Seeking the Current wowed audiences across New Hampshire with the sublime beauty of Québec’s Romaine River – a wild, natural wonder that will essentially be destroyed by a new complex of hydropower projects, now under construction.  This complex is only one part of Hydro-Québec’s ongoing building boom – the keystone of the Canadian utility’s aggressive strategy to increase exports to the United States. The film also showed filmgoers that there are better, cheaper alternatives to new hydropower, including wind, solar photovoltaic, solar hot water, biogas, and investments in energy efficiency.  If these alternatives were scaled up and put in place throughout the province, Québec could still export more power to the United States – but without constructing new dams and reservoirs.

During the discussions after the film (one of which you can watch here), we heard the same question again and again – what can we do here in New England? The filmmaker Nicolas Boisclair observed that Hydro-Quebec’s strategy relies on opening new “doors” to New England and other export markets – like the Northern Pass transmission project. That’s another reason why CLF sees the permitting process for Northern Pass as so important – it is our opportunity to scrutinize whether we should open the door and on what terms, given all the impacts of the Northern Pass transmission project and the new Canadian hydropower the project makes possible.  And there is still time for all of us to tell the lead federal permitting agency for Northern Pass – the U.S. Department of Energy (DOE) – to do its job by fully considering the impacts of Canadian hydropower.

Understanding Northern Pass’s power source is fundamental to understanding Northern Pass, especially with the developers of the project touting the environmental benefits of Canadian hydropower at every opportunity. PSNH President Gary Long even has said “we wouldn’t be doing” Northern Pass if it didn’t provide a “greener, cleaner energy future.” But when it comes to scrutinizing all the impacts of that same hydropower in the permitting process, the developers change their tune, arguing that the impacts of Hydro-Québec’s strategy to build more hydropower projects and export more power to the northeastern United States are “beyond the reach of” federal law.

On this point, the developers are wrong. Federal law requires that all direct and indirect effects of the Northern Pass project be analyzed and considered as part of DOE’s environmental review. In the words of the Council on Environmental Quality – the office that oversees all federal environmental reviews – “agencies must include analysis of reasonably foreseeable transboundary effects of proposed actions in their analysis of proposed actions in the United States.” The impacts of hydropower in Canada – so stunningly documented in Seeking the Current and so much more worse for the climate than the misleading story Northern Pass developers like to tell – are “reasonably foreseeable” consequences of the Northern Pass project, and the Department of Energy must consider them, alongside all the potential impacts of building a large-scale transmission line through New Hampshire. CLF made this clear in our comments to DOE a year ago, but it is critical that DOE hear from as many voices as possible.

Please join CLF in calling on the Department of Energy to consider the impacts of Northern Pass hydropower in Canada.  With only a few clicks, you can take action here.

NU/NStar & FERC Order 1000: Our Shared Energy Future

Mar 22, 2012 by  | Bio |  Leave a Comment

A few weeks ago I attended a conference in Washington, DC that brought together environmental groups from all over the country. In speaking with my colleagues, I was reminded of how this country is a patchwork quilt: each of us brought a unique set of challenges, a strong independent sense of identity, and solutions to regional challenges – solutions that are sometimes adopted at the national level. This certainly is true of New England.

Over the last year, two events have emphasized the importance of interregional coordination. In the process, they have reminded me of New England’s long history of regional cooperation to advance nation leading clean energy projects, and of the way in which those have been adopted on the national stage.

The first of these issues is FERC Order 1,000 – a significant reform to the Federal Energy Regulatory Commission’s position on “electric transmission planning and cost allocation requirements for public utility transmission providers” issued in June of 2010. That Order, and material explaining it, can be found on the FERC website. The new rules announced in that Order mandate that utilities operating wholesale electricity systems across the country engage in a process of regional planning. Here in New England, we have been doing that for as long, if not longer, than anywhere else in the country, so that part of the order will prompt new regional innovations largely elsewhere in the country. Another part of the order instructs regional operators of the electric grid to consider the public policy mandates of the states in their region in the planning they do for their part of the grid. The New England states have a variety of innovative policies intended to bring about a clean energy future. How our regional grid operator accounts for those in its planning is very likely to break ground for the rest of the country.

Similarly, the recent breakthrough settlement agreement by the Patrick Administration in the proposed merger between NStar and Northeast Utilities also reminded me of the need for regional coordination. Consider the scale of the proposed utility: As The Boston Globe reported, “the proposed $17.5 billion merger… would create the largest utility in the region, [and serve] nearly 3.5 million electric and gas customers from Westport, Conn., to Pittsburg, N.H., near the Canadian border.”

With a reach extending from southern Connecticut to Northern New Hampshire by way of Boston, the resulting utility has obligations under a variety of critical state policies intended to protect the environment and build a resilient clean energy economy. The right to operate as a state-sanctioned monopoly is conditioned on the utility meeting those obligations. The initial terms of the proposed merger did not meet those requirements; the merger as revised by the settlement, as my colleague Sue Reid said, “ensures that this powerful new utility will be in lockstep with Massachusetts’ nation-leading clean energy policies and propel the state forward instead of backwards in implementing them.”

This cases highlight the need for advocacy groups to be able to field their teams  on a scale and in a manner that that rises to the challenge of the moment. The NU/NStar merger required us to play on a regional scale; FERC Order 1,000 provides a chance to use the federally regulated planning process to advance critical state policies that are designed to build a cleaner and thriving New England. The challenges we face, and the institutions we engage (like utilities), are large and extend across our region and beyond, not respecting traditional boundaries. CLF must meet this challenge with size, scale, intentions, goals, and strategies that are appropriately sized to meet those challenges.

Given New England’s strong tradition of leadership on energy and environmental issues, I have confidence we have the tools required. However, as my conversations in DC emphasized, what is appropriate here in New England is not appropriate for every region.

Given the differences between the various regions of the country, and various areas within those regions, I wonder: To what extent can we successfully plot a common future? These questions are as relevant within New England as between regions.

Driving south from Acadia National Park in Maine or Hanover, New Hampshire, or east from Springfield, MA and Hartford, CT the scenery changes, the weather warms and the population becomes more dense. Though each place is in New England, each feels very different – and, if you ask someone on the street, chances are they’ll tell you just how unique and independent their town or city is. The same is true as you travel north from Atlanta or NYC to Boston, or east from Chicago or San Francisco. Within New England, as within our country, our differences can be easier to see than our shared future, but it is the latter that requires our attention.

More and more, we have the tools. That puts us in a good position to work together, town by town, region by region, for a thriving New England, and a thriving country.

Don’t Miss Your Chance to See Seeking the Current and Catch a Replay of Our Webinar on Importing Canadian Hydropower

Mar 13, 2012 by  | Bio |  Leave a Comment

Seeking the Current filmmaker Nicolas Boisclair (photo: Red River Theatres in Concord)

The New Hampshire tour of Seeking the Current is off to an amazing start. So far, the documentary about Hydro-Québec’s Romaine River hydropower project has played to blockbuster audiences in Colebrook, Wolfeboro, Wilton, and Concord (including a sell-out last night), and we’ve had a great time participating in lively post-film discussions with filmgoers and the film’s director, Nicolas Boisclair.  Please join Nicolas and CLF at the remaining screenings and discussions that are coming up this week:

We also have a free showing of the film scheduled for April 5 in Keene, with a post-film discussion:

If you’ve seen the film, were as impressed as we were, and want to help show Seeking the Current in your community in the coming months, please let me know at ccourchesne@clf.org. We’d love to work with you to make it happen.

In conjunction with the film’s New Hampshire tour, CLF co-hosted a successful webinar last week on the environmental and energy implications of importing more large-scale hydropower into New England. During the webinar, Nicolas shared a preview of Seeking the Current, and participants learned how the issues raised by the film are critical to a full understanding of proposals to import more hydropower, including the Northern Pass project. You can download an audio-visual archive of the webinar at this link (~100 MB .wmv file; Windows compatible only).  To play the webinar, you may need to download some additional software, which you can access here.

Thanks to our many terrific co-sponsors (all of which are noted here) and the extraordinary people who helped bring Seeking the Current and its powerful message to New England audiences. Enjoy the show!

Join CLF Next Friday March 9 for a Special Webinar on Importing Canadian Hydropower

Mar 1, 2012 by  | Bio |  Leave a Comment

With Northern Pass and other new transmission projects on the horizon, CLF and other leading New Hampshire environmental organizations are presenting a special free webinar on what it really means for New England to import more hydroelectric power from Canada.

The webinar will be next Friday, March 9, 2012, 2:30 to 4pm EST. Click here to register. All you’ll need is a computer and an Internet connection. Please join us, and spread the word to friends, family, and colleagues. The webinar is sponsored by CLF and our friends at the Appalachian Mountain Club, Conservation New Hampshire, The Nature Conservancy in New Hampshire, and the Society for the Protection of New Hampshire Forests (SPNHF). 

A scene along the Romaine River from Seeking the Current (copyright Chercher le Courant)

The idea is to provide an accessible summary of the environmental and energy implications of imports, including the often-overlooked impacts of the new hydropower developments in Canada that will supply the power. One of the key questions is what new imports will really mean for the climate, and I’ll explain the findings of a recent report commissioned by CLF on the greenhouse gas emissions of hydropower. As we’ve often pointed out, whether and how to import more hydropower from Canada is a critical issue for the entire region’s energy future. And it’s not just about New Hampshire and Northern Pass — just last week, the developer of the Champlain Hudson project in New York announced that it is moving forward with a revised proposal for an underwater and underground transmisssion line between Canada and New York City that will have the support of state officials, municipal governments, and environmental groups.

During the webinar, you’ll hear from me, and also from Tom Irwin, CLF Vice-President and CLF-NH Director; Ken Kimball, AMC Director of Research; and Will Abbott, SPNHF Vice President for Policy and Land Management.

The webinar will feature a special guest appearance by Québecois filmmaker Nicolas Boisclair, who will be in New Hampshire this month for a series of screenings of his documentary film, Seeking the Current, which shines an unsparing light on Hydro-Québec and its ongoing $8 billion hydropower project on the Romaine River. We’ve put all the details on the screenings (and the webinar too) at this link.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.