The “New Route” for Northern Pass Won’t Cure Its Failings

May 24, 2012 by  | Bio |  Leave a Comment

This summer, New Hampshire is bracing for news of the Northern Pass project’s future and its “new route.”

It’s now been nearly a year since the federal permitting process for the Northern Pass project was put on indefinite hold. North of Groveton, New Hampshire, the developer – Northern Pass Transmission LLC (NPT) – is still working behind tightly closed doors to string together a new section of the project route, where there are no existing transmission corridors, by paying landowners substantial sums for property – in many cases, well above market value.

Earlier this month, the chief operating officer of NPT’s parent company, Northeast Utilities, told investors:

Where we are right now is in procuring the last 40 miles of the right-of-way, and I can tell you we are making very, very strong progress in lining up the right of way. I think we’re on track for the middle of the year, approximately August timeframe to have the right-of-way secured and then to be prepared to file with the [U.S. Department of Energy] the route….

NPT’s apparent plan (assuming it really can overcome the considerable obstacles to a new route):

Not so fast. Before the news arrives (if it does), it’s worth remembering that whatever new lines the developer manages to draw on the map do nothing to change the project’s DNA or to demonstrate that the project will benefit New Hampshire. A brief review is in order:

Where are the benefits for New Hampshire?

Through  costly marketing efforts, NPT has been trying to sell New Hampshire on the tremendous economic and environmental benefits of Northern Pass. But the supposed benefits just don’t hold up to scrutiny:

  • Reduced emissions from “clean power”?

In terms of greenhouse gas emissions, CLF’s report on the most recent science demonstrated that new hydropower projects to supply power for Northern Pass are much worse for the climate than NPT’s false advertising claims have led the region to believe and are not meaningfully better than natural gas power plants (the power NPT predicts that Northern Pass would replace) in the early years after reservoirs are developed. As a result, contrary to mistaken but widely disseminated assumptions, importing hydropower from Canada is not a short-term solution that will reduce New England’s or New Hampshire’s carbon emissions. Indeed, the current proposal would have the perverse effect of protecting – rather than hastening the transition away from – PSNH’s low-performing, high-emitting power plants, which are New Hampshire’s largest source of greenhouse gas emissions. (Despite marketing the project based on its “clean” source of the power, NPT also refuses to acknowledge the relevance or importance of the troubling damage to ecosystems and communities that large-scale hydropower causes in Canada.)

  • Lower electric rates?

Those who would live with the new transmission lines, customers of NPT affiliate PSNH, are the least likely to benefit. Despite nearly two years of promises that PSNH would announce a plan to purchase Hydro-Québec hydropower for New Hampshire residents, there is still no agreement to do so. Any modest effects on the region’s wholesale electricity rates (which NPT’s consultant predicted based on outdated economic assumptions about energy costs) don’t translate into lower rates for PSNH customers (who instead are stuck paying the bill for PSNH’s inefficient and dirty power plants). In fact, if Northern Pass succeeds in lowering wholesale rates, it will likely worsen PSNH’s death spiral of increasing rates and fewer customers, leaving those residents and small businesses still getting power from PSNH with higher bills.

  • Growing New Hampshire’s clean energy economy and jobs?

There is a substantial risk that Northern Pass would swamp the market for renewable energy projects in New England, especially if state laws are amended to qualify Hydro-Québec power as “renewable.” Furthermore, the project’s high voltage direct current technology means that its massive investment in transmission capacity will wholly bypass the potentially fertile ground for renewable energy development in northern New England. Whatever the short-term construction jobs required (and NPT’s estimates are disputed), the current Northern Pass proposal may diminish the prospects for New Hampshire’s clean energy economy, including needed permanent jobs in the renewable and energy efficiency sectors.

No regional plan addressing new imports

Québec continues to implement its ambitious plan to develop more wild Boreal rivers into a new generation of massive hydropower projects, which will increase its export capabilities. This January, Hydro-Québec commissioned the final turbine at its latest hydropower facility (Eastmain 1-A) and will commission other turbines (at Sarcelle) as part of the same overall project later this year. Construction at the $8 billion Romaine River hydropower project (the subject of the film Seeking the Current) has begun and is ongoing, with the first unit expected to come online in 2014. Northeast Utilities has affirmed that Northern Pass will tap the power from these new projects. Meanwhile, Northern Pass competitors are moving forward with new transmission projects in eastern New England and in New York, among others:

Northern Pass and competitor transmission projects (source: ISO-NE)

More than a year ago, CLF and others urged the Department of Energy to weigh the region’s energy needs and develop a strategic regional plan that would determine a well-informed role for new Canadian hydropower imports in the northeastern United States’ energy future – before moving forward with the permitting process for Northern Pass. NPT’s only response was that responsible planning – encompassing the other pending transmission projects and a full consideration of the reasonable alternatives – would unacceptably delay its project – a truly ironic claim given NPT’s own, unforced, ongoing delay. More incredibly, the Department of Energy has so far sided with NPT, without explaining why.

So as Québec builds more dams and NPT buys up land, our region has no plan of its own. With no framework to understand the nature and extent of the appropriate role for Canadian hydropower, it is difficult if not impossible to make a sound, well-informed decision on whether Northern Pass – or projects like it – should proceed.

Community and grassroots reaction throughout New Hampshire

Since Northern Pass was announced in 2010, the project has inspired a broad-based and spirited movement of people throughout New Hampshire to oppose the current proposal. Last spring, there were massive turnouts at the Department of Energy’s public hearings on the project, with literally thousands attending and providing written and verbal comments both questioning the merits of the current proposal and urging a thorough environmental review. And earlier this year, a coalition of citizens and organizations of many political stripes succeeded in persuading New Hampshire’s legislature to enact a bill preventing projects like Northern Pass from using eminent domain. In another effort, more than 1,500 donors contributed total of $850,000 to enable the Society for the Protection of New Hampshire Forests to preserve the treasured New Hampshire landscape surrounding the historic Balsams resort, including a parcel that NPT had sought to purchase as part of Northern Pass’s transmission corridor. To date, town meeting voters in 32 local communities have passed resolutions and ordinances against the current proposal. Critically, most of these communities are located along the NPT’s “preferred route” that follows PSNH ‘s existing transmission corridor, south of any “new route” that NPT may announce.

NPT’s refusal to consider routing and technological alternatives

At every turn, NPT has rejected calls for in-depth consideration of potential alternatives to its current proposal, including use of an existing high-voltage transmission corridor that extends from Canada, through Vermont and western New Hampshire, to Massachusetts; burying transmission lines in transportation corridors, as is proposed in the New York and eastern New England projects mentioned above; or adding capacity to that same New York project, consistent with that project’s original proposal (it has since been scaled back). Indeed, Northern Pass’s response to the public’s opposition to the project was to “withdraw support” for alternative routes and double down on its “preferred route.” While this stance may be in the economic interest of NPT and PSNH, it’s grossly at odds with a fair, well-informed permitting process that would vindicate the public’s interest in a solution with minimal environmental and community impacts.

If and when NPT comes back from its year of buying up North Country land and relaunches its effort to secure approval of the Northern Pass project, with the only change to the proposal consisting of a new line on the map north of Groveton, there should be no mistake: the fundamental flaws in the current proposal remain. Likewise, whatever NPT’s “preferred route,” CLF remains as committed as ever to securing a comprehensive and rigorous permitting process that identifies superior alternatives and a final outcome that moves us toward – and not away from – a clean energy future for New Hampshire and the region.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northern-pass), and take a look at our prior Northern Pass posts on CLF Scoop.

Northern Pass Attacks Land Conservation in New Hampshire, Loses in the First Round

Dec 28, 2011 by  | Bio |  1 Comment »

courtesy Society for Protection of New Hampshire Forests

Last week brought a fitting capstone to the botched year-long rollout of the Northern Pass project.  In a disturbing turn of events, the project developers sought to scuttle a historic plan to preserve a storied wilderness in New Hampshire’s North Country. Their attempt failed, but what the episode says about their future tactics is anything but encouraging for New Hampshire and the region.

Northern Pass Transmission, LLC (NPT) – a partnership between Northeast Utilities and NSTAR – has spent 2011:

It has been clear for some time that the current proposal is really about two things – securing profits for Hydro-Québec and propping up NU subsidiary PSNH’s weakening bottom line. CLF is not alone in wondering: what’s in it for New Hampshire?

Last week was a vivid preview. And if you care about New Hampshire’s iconic wilderness landscapes or the organizations that protect them, it’s not a pretty picture.

Earlier this fall, we learned that NPT was bidding to purchase a strip of land through one of the North Country’s crown jewels – the magnificent Balsams estate in Dixville Notch – from its owner, the Neil Tillotson Trust.

Enter the Society for the Protection of New Hampshire Forests (SPNHF), a key collaborator with CLF on Northern Pass advocacy and one of the state’s leading land conservation organizations. Culminating a decade of effort to preserve the Balsams landscape, SPNHF secured from the Trust a conservation easement over 5,800 acres of spectacular wilderness surrounding the resort, provided that SPNHF raises $850,000 for the easement by mid-January. (You can follow the effort here. Word is that, as of today, SPNHF is nearly a third of the way there.) The easement would preclude any transmission corridor.

The land is an ecological and scenic marvel, and the deal marks a historic land preservation achievement for SPNHF, the Trust, and New Hampshire as a whole.

The Balsams Resort in winter (photo credit: j-fi/flickr)

NPT’s bizarre and audacious response: launch a legal attack on the conservation plan.

Last week, NPT asked the state Attorney General’s Office to disapprove the easement on the ground that NPT’s earlier bid was higher. Then on Friday of last week, NPT made a very public offer to buy both the transmission corridor and the conservation easement, which would secure a right to site the Northern Pass project on the Balsams property. The last move was particularly odd because most bidding wars don’t involve publicly bullying a seller – a respected charitable trust no less – into accepting an offer.

As noted in the Concord Monitor and on NHPR, news came late Friday afternoon that the state Attorney General’s Office had approved the sale of the conservation easement to SPNHF, despite NPT’s objections and richer offers. The approval letter noted that it was well within the Trust’s charitable purposes and discretion to sell the easement to SPNHF for less than NPT’s offer. In other words, the Trust should be free to decide that preserving the Balsams property for the benefit of the North Country is more important than the Trust’s financial return.

Why was NPT’s attack on the conservation plan so troubling?

  • NPT sought to undermine land preservation efforts throughout New Hampshire. Land preservation almost always requires generosity – the landowner’s decision to accept less than market value or to make an outright donation of an easement. If it had been successful, NPT’s legal attack would have left no room for such generosity, granting any private developer the power to block a landowning non-profit’s preservation of its land whenever the developer offered more money than the conservation organization or community that would hold the conservation easement.
  • NPT is on war footing.  NPT is pursuing the equivalent of scorched earth litigation, resorting to strong-arm tactics and legal appeals to the state, including a threat of litigation to block the SPNHF easement that, as of today, remains on the table. At this early stage of the project’s permitting, this is exactly the opposite of what we need – a well-informed regional and statewide dialogue about our energy future, the project’s potential role if any, and the alternatives to traditional overhead lines along NPT’s proposed route.
  • NPT has broken its promise to find a route “that has support of property owners.”  The Trust made a decision not to sell to NPT; within days, NPT was crying foul to a state official.  NPT’s appeal to the state reveals, for all to see, that NPT will respect the will of landowners only when that will is to sell NPT the land it wants. As others pointed out before the Attorney General Office’s decision, NPT’s carefully-worded disinterest in using eminent domain (except as a “very last resort,” in the words of PSNH President Gary Long) is no longer credible, if it ever was.
  • NPT is willing to spend huge sums, but only to get the project it wants. Without hesitation or public discussion, NPT offered what amounts to a $1 million donation (of Hydro-Québec’s money) to the Trust, including a $200,000 grant to Colebrook Hospital and the money for the Balsams conservation easement. Clearly, NPT is willing to spend millions above and beyond market costs to get the route it wants, even as it rejects as too costly alternatives that could be better for New Hampshire.

Above all, the Balsams episode shows that NPT is not pursuing the Northern Pass proposal as a public-minded enterprise for the “good of all of New Hampshire.” With so much at stake for the region and New Hampshire, CLF’s work of 2012 is to secure a searching and rigorous public review process that will scrutinize every element of the Northern Pass project and ensure that the public interest – and not the dollars in NPT’s coffers – determines the project’s fate.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass), and take a look at our prior Northern Pass posts on CLF Scoop.

What the Keystone XL decision should mean for Northern Pass

Nov 17, 2011 by  | Bio |  Leave a Comment

Protesters against Keystone XL - November 6, 2011 (photo credit: flickr/tarsandsaction)

Last week, a major disaster for our climate and our nation’s clean energy future was averted – at least for now – when the Obama administration announced that it won’t consider approving the Keystone XL pipeline’s border crossing permit before it reconsiders the Keystone XL pipeline’s environmental impacts and the potential alternatives to the proposal on the table.  For all the reasons that my colleague Melissa Hoffer articulated in her post last week, the Keystone XL victory was a resounding, if limited, triumph with important lessons for environmental and climate advocates across the country as we confront, one battle at a time, the seemingly overwhelming challenge of solving the climate crisis.

The Keystone XL decision also hits home in another way. It sends an unmistakable signal that the federal government’s review process for New England’s own international energy proposal – the Northern Pass transmission project – needs the same type of new direction.

The parallels between the State Department’s Keystone XL environmental review and the mishandled first year of the U.S. Department of Energy’s review of Northern Pass are striking. In both cases, we saw:

  • Troubling, improperly close relationships between the developer and the supposedly independent contractors conducting the environmental review, with unfair and inappropriate developer influence on the review’s trajectory, undermining the public legitimacy of the review process;
  • An extraordinary grassroots uprising against the proposal from diverse groups of residents, landowners, communities, businesses, and conservation and environmental groups;
  • Massively expensive lobbying and public relations campaigns by proponents designed to confuse and mislead lawmakers and the public
  • Repeated failures by permitting agencies to ensure fair, open, and truly comprehensive review of the full range of impacts, including climate impacts, and the reasonable alternatives for meeting our energy needs in other, less environmentally damaging ways.

With all the legal, procedural, and substantive deficiencies our national advocate colleagues have been pointing out for years, the Keystone XL review (before last week) is a dramatic example of what we can’t allow to happen with Northern Pass. Right now, things don’t look good – it appears that the Department of Energy is engaging in an “applicant-driven,” narrow review of a few potential project routes, not the broad, searching analysis CLF and many others have demanded again and again (and again).  Last week’s decision to conduct a wide-ranging new review of Keystone XL shows that there is still the opportunity (and now a clear precedent) for the Department of Energy to bring the same spirit of renewed scrutiny and public responsiveness to its review of Northern Pass.

New Hampshire and New England deserve an impartial, comprehensive, and rigorous review of the Northern Pass project – and all reasonable alternatives – by the permitting agencies entrusted with protecting the public interest. Indeed, what we need now is a serious regional plan that addresses whether and how best to import more Canadian hydropower into New England and the northeastern U.S. With huge projects like Keystone XL and Northern Pass on the table, our nation’s energy future is at stake, and it has never been more important – for our communities, economy, natural environment, and climate – to get it right.

For more information about Northern Pass, sign-up for our monthly newsletter Northern Pass Wire, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass), and take a look at our prior Northern Pass posts on CLF Scoop.

Interested in Northern Pass? Sign up for CLF’s new eNewsletter – Northern Pass Wire!

Oct 31, 2011 by  | Bio |  Leave a Comment

Are you concerned about the Northern Pass transmission project? Do you want to learn more about what it could mean for New Hampshire and New England’s energy future, for our climate, for energy rates, and for the communities and natural environment of New England and Québec? Do you want to keep up with the latest developments as the project progresses through the permitting process?

If you answered yes to any of these questions, you’ll want to sign up for CLF’s new email newsletter – Northern Pass Wire.  In a concise format, Northern Pass Wire will provide the latest news and analysis regarding the Northern Pass project direct from CLF advocates, with links to additional resources from CLF’s Northern Pass Information Center, our latest Northern Pass posts here on CLF Scoop, and CLF’s recent legal filings. Northern Pass Wire will also keep you informed about ways you can get involved and make your voice heard as the permitting process for the Northern Pass project continues. We expect to publish Northern Pass Wire about once a month, and perhaps more frequently when events warrant. The first edition can be previewed here, and you can sign up to get Northern Pass Wire here.

Please sign up and encourage your family, friends, and colleagues to do the same!

Click on the image to preview the first edition of CLF's Northern Pass Wire

New England still deserves a fair, big-picture review of Northern Pass, despite developers’ delay

Oct 26, 2011 by  | Bio |  1 Comment »

photo credit: Hope Abrams/flickr

Here in New Hampshire, the leaves have turned.  What hasn’t changed is that the environmental review of the Northern Pass proposal remains stalled while the project developers – Northeast Utilities (and its subsidiary Public Service Company of New Hampshire) and NSTAR – seek a new route for the northernmost 40 miles of the project.  It’s a disgrace that the U.S. Department of Energy (DOE) has so far refused to use the developers’ significant delay to assess the nature and extent of New England’s need for Canadian hydropower and to develop an appropriate plan to bring that power into the region, as CLF and others have been requesting since April.

While DOE is in a holding pattern, CLF is continuing to fight for a fair and comprehensive environmental review of the Northern Pass project.  Earlier this month, CLF filed new comments with DOE, supplementing the detailed comments we filed in April.  Our new comments address:

  • Why CLF has renewed concerns about DOE’s control over its new environmental review contractors.  Based on our review of the Memorandum of Understanding between Northern Pass, DOE, and its new contractors, posted here (PDF), we explain that Northern Pass could still have an unfair and inappropriate influence on the content of the environmental impact statement and the schedule for completing it.
  • What the Northeast Energy Link proposal means for the Northern Pass environmental reviewThe recently announced Northeast Energy Link proposal, along with the Champlain Hudson Power Express project, makes it clearer than ever that we need a regional assessment of our energy needs.  These other two transmission projects also show that burying transmission lines in transportation rights-of-way is an abundantly reasonable alternative to overhead lines.
  • How Northern Pass hasn’t clearly disclosed the source of power for the project.  We bring to DOE’s attention important information, obtained by CLF through its cross-examination of an executive of Northeast Utilities before Massachusetts regulators, that the source of Northern Pass’s power is likely to be new hydroelectric projects that Hydro-Québec is now in the process of designing and building.  CLF is especially troubled by the new information because the impacts of the project are much more significant if it causes the construction of new dams and the associated negative environmental impacts, including well-documented spikes in early greenhouse gas emissions from flooded land.  Northern Pass and its parent companies have consistently failed to acknowledge that these emissions undermine their claims about the reductions in emissions the project will supposedly provide.

A copy of our new comments is available here.  We also filed a Freedom of Information Act request with DOE, seeking to obtain a copy of the “Consulting Services Agreement” between Northern Pass and the environmental review contractor team.  The Memorandum of Understanding suggests that this separate contract includes important information on the budget and schedule for the environmental review, and the public deserves to know these details.

With the permitting process due to continue when Northern Pass announces a new northernmost route, CLF will be launching new ways to keep you informed about the latest Northern Pass news and the best ways for you to get involved and make your voice heard. Please stay tuned!

For more information about Northern Pass, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass) and take a look at our prior Northern Pass posts on CLF Scoop.

More time to make your voice heard on the Northern Pass project

Apr 19, 2011 by  | Bio |  1 Comment »

Last Friday, the U.S. Department of Energy (DOE) announced in the Federal Register that it’s extending to June 14, 2011 the deadline for submitting scoping comments on the proposed Northern Pass electric transmission project.

UPDATE:  As of June 15, 2011, DOE has again reopened the comment period – this time indefinitely – pending the submission of updated route information from Northern Pass.  See more here.

This extension of the public comment period comes on the heels of huge turnouts at DOE’s seven public meetings in March and the news (noted on NHPR here and in the Concord Monitor here) that the developer of the project wants DOE to stop considering several alternative routes for the project in favor of its original preferred route.

DOE’s extension means that you still have an important opportunity to help shape the environmental impact statement (EIS) and influence DOE’s decision on the project.  The EIS will be a detailed statement of the environmental, social, and economic impacts of the Northern Pass proposal and alternatives.

What Should I Address in My Comments?

CLF encourages you to raise any reasonable concern or question about the proposed Northern Pass project and alternatives:

  • Describe how the project could affect the natural resources that you value.
  • Explain your concerns about the potential impacts of the project on scenic landscapes, communities, wildlife, forest resources, wetlands, recreation areas, the energy sector, and the local economy.
  • Demand that DOE analyze the environmental impacts associated with generating the hydroelectric power that the project will transmit.
  • Insist that DOE rigorously examine all reasonable alternatives to the project, including alternative project designs (like burying the lines in railroad or highway rights of way) and options that would generate or save the same amount of power here in New England (like local renewable energy, energy efficiency, or conservation programs).
  • Join CLF’s request for a comprehensive EIS that assesses New England’s need for Canadian hydropower and develops a more holistic, proactive plan for addressing any such need (as opposed to reacting to project-specific proposals such as Northern Pass)

How Do I Submit Comments?

To comment, email DOE at Brian.Mills@hq.doe.gov or use DOE’s Northern Pass EIS web form by June 14, 2011.  UPDATE: As mentioned above, the deadline for comments has been extended again – to a date yet to be determined.

For More Information

DOE must step back and consider Northern Pass in its broader context

Apr 13, 2011 by  | Bio |  2 Comment »

Daniel Johnson Dam, north of Baie-Corneau, Québec

Last night, CLF filed detailed written comments with the U.S. Department of Energy (DOE) regarding the scope of the Environmental Impact Statement (EIS) for the Northern Pass project. (A PDF of our comments is here.)   First and foremost, our comments urge DOE to stay the Northern Pass proceeding and instead conduct a comprehensive, regional analysis (a comprehensive EIS) of the region’s need for Canadian imports, to enable sound planning as opposed to the piecemeal, project-by-project approach DOE is currently taking by simply reacting to the permit applications of private entities like Northern Pass.   

Our comments expand on the remarks (PDF) I made at the Pembroke scoping meeting last month and come on the heels of yesterday’s major news that (1) Northern Pass wants DOE not to consider some alternative routes it included in its Presidential Permit application and also needs more time to discuss additional potential routes through the North Country (a PDF of Northern Pass’s filing is here and coverage on NHPR here) and (2) DOE is reopening the scoping public comment period through a date to be determined in June.  The fact that Northern Pass itself has asked for a delay to reconsider aspects of its project is an even stronger indication that DOE can and should take the time it needs to undertake a full regional analysis through an open, and collaborative public process.   

(more…)

What’s the plan for the Northern Pass environmental review?

Mar 31, 2011 by  | Bio |  Leave a Comment

If the U.S. Department of Energy (DOE) does its job right, the environmental review of the Northern Pass project – the largest infrastructure project in recent New Hampshire history – will be a massive and complex undertaking, analyzing all alternatives to the current proposal and describing the many social and environmental impacts of the project.  That’s why it’s critical that DOE begin its work with the right plan – one that takes into account the tremendous public input DOE has received during the ongoing scoping process and that also reflects DOE’s technical expertise, especially regarding the possible technological alternatives to the current proposal.  (Information on the scoping process and how to submit comments to DOE is here – the deadline for written comments is April 12.)

Today, in a joint letter to DOE, CLF and several partners renewed their request (also made at the mid-March scoping meetings) for DOE to release a report – before it begins work on the draft Environmental Impact Statement (EIS) – identifying the alternatives DOE plans to study in depth, the alternatives it plans to exclude from the analysis, and the categories of social and environmental impacts that it will consider.  We believe that DOE should not only prepare such a report, but also provide the public the opportunity to comment on it.

The report on the scoping process that DOE currently intends to issue – one that simply summarizes public input – is not enough, especially for this project.  The project application provided almost no information on alternatives and environmental impacts (something CLF and others vehemently objected to months ago), and that lack of information has undermined the public’s ability to provide meaningful feedback during the scoping process as a result.

Before DOE and the EIS contractor it ultimately selects to replace its original contractor begin studying the project and its alternatives behind closed doors, the public deserves to know DOE’s plan and to have the chance to suggest changes to that plan. Otherwise, DOE may “re-emerge” from its work months from now with a document that misses important alternatives and will be very challenging to change – a result that would be problematic for DOE and the public alike.  DOE needs to get it right the first time, and the public should be invited to help ensure that DOE has the right plan to do so.

For more information about Northern Pass, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass) and take a look at our prior Northern Pass posts on CLF Scoop.

Huge turnout at first Northern Pass public meeting

Mar 15, 2011 by  | Bio |  Leave a Comment

As reported in the Concord Monitor and the Manchester Union-Leader and on WMUR, the public was out in force last night at the first of seven public scoping meetings kicking off the Department of Energy’s (DOE’s) environmental review of the Northern Pass project. More than 400 attended, and about 50 people expressed their views on the project and the issues that should be addressed in DOE’s environmental impact statement (EIS).  It was a testament to the value of the National Environmental Policy Act (NEPA), which requires that federal agencies encourage and consider public input on the environmental and other effects of agency decisions and potential alternatives to those decisions.  It was also clear that the proposal, as currently presented and described by the developer Northern Pass Transmission, LLC, has very little public support; dozens of speakers from up and down the proposed route expressed opposition to the current proposal.

During the formal commenting session, I made brief remarks to insist that DOE conduct a wide-ranging and rigorous NEPA process, and I also requested that DOE provide more opportunities for public input by (1) extending the period for public comments on the scope of the EIS to May 3, and (2) releasing a proposed EIS scope and outline for public review and comment, before major efforts are undertaken to draft the EIS, to ensure that DOE is considering all relevant impacts and alternatives.  CLF’s press release about the meeting is here, and my prepared remarks are here.  CLF will be following up my remarks at the meeting last night with written comments as well.

If you have concerns about the project, know of environmental and community impacts that you think DOE should consider, or alternatives to the project that DOE should analyze, you can participate in the scoping process by speaking at one of the remaining meetings, or by submitting written comments to DOE by the deadline (currently April 12).  All the details you need are in CLF’s one-page handout on the scoping process.

For more information about Northern Pass, visit CLF’s Northern Pass Information Center (http://www.clf.org/northernpass) and take a look at our prior Northern Pass posts on CLF Scoop.