First in New England: PSNH Is the Region’s Top Toxic Polluter

Jan 6, 2012 by  | Bio |  1 Comment »

The nation’s attention may be focused right now on the twists and turns of New Hampshire’s First in the Nation primary. But new pollution data from the Environmental Protection Agency put a more troubling spotlight on New Hampshire – and on its largest utility, Public Service Company of New Hampshire (PSNH). 

According to the data, PSNH is the region’s top toxic polluter, and PSNH’s coal-fired power plant in Bow, Merrimack Station, releases more toxic pollution to the environment than any other facility in New England. Because of PSNH, New Hampshire as a whole is first in New England in toxic pollution.

The numbers tell a striking story.  In 2010, Merrimack Station released 2.8 million pounds of toxic chemicals to the environment, mostly in air pollution.  That’s an astonishing 85% of the 3.3 million total pounds of toxic pollution released in New Hampshire in 2010. When you add in PSNH’s coal-fired Schiller Station in Portsmouth and its gas and oil-fired Newington Station in Newington, PSNH was responsible for a total of 3 million pounds of toxic pollution in 2010, more than 90% of New Hampshire’s toxic pollution. 

PSNH’s pollution isn’t saving energy consumers anything – PSNH’s rates are among the highest in New England because of the escalating costs of maintaining PSNH’s old, inefficient power plants. And those rates are slated to steadily climb as PSNH customers – mostly residents and small businesses – watch large commercial and industrial customers reject the costs of PSNH’s above-market coal-fired power to buy from cost-effective, competitive suppliers. As a result, most New Hampshire residents are left with the raw deal of paying among the highest rates for the dirtiest power in New England.

The data is a fresh reminder of why CLF is fighting so hard to hold Merrimack Station accountable for violating the Clean Air Act. In November, CLF made the case in federal court that PSNH’s failure to obtain permits for changes at Merrimack Station has meant that PSNH has evaded requirements for state-of-the-art pollution limits that would reduce its emissions of a wide range of toxic and other pollutants.

It’s true that PSNH’s much-touted and hugely expensive scrubber project now coming online at Merrimack Station will ultimately reduce some types of toxic pollution to the air. But PSNH wants to increase its energy rates by 15% to pay for the scrubber. Other required pollution controls, including those imposed by important new federal rules, may lead to further costs. This will make PSNH’s power plants an even worse deal for New Hampshire ratepayers.

Merrimack Station also sends more carbon dioxide into the air than any other source in New Hampshire, and the scrubber won’t change that. Burning coal is a dirty way to generate power that imperils the climate, and it is time for New England to abandon it for cleaner alternatives that safeguard our health and environment and transition us toward a new energy system.

New Hampshire may never be willing to relinquish its leading spot on the presidential primary calendar. But living with New England’s largest source of toxic pollution despite its unacceptable costs – to ratepayers and the environment – is a distinction that New Hampshire should be doing everything in its power to lose.

Storm clouds gather for New Hampshire electric ratepayers

Oct 19, 2011 by  | Bio |  2 Comment »

photo credit: l . e . o/flickr

With each passing day, the dire reality of PSNH’s coal-fired business model is becoming clearer in New Hampshire.  The cost of operating PSNH’s obsolete power plants continues to grow, accelerating the Company’s death spiral where fewer captive ratepayers are saddled with unsustainable above-market rates as more PSNH customers choose to buy power from better managed competitive suppliers.  We are also learning that Northern Pass will make the situation worse for ratepayers, not better, and that PSNH and its Northern Pass partners are poised to pull in huge profits.  In just the last few days:

  • PSNH revealed that, as it has begun bringing online its $450 million scrubber project at PSNH’s 50 year old coal-fired Merrimack Station, the bill is now coming due. If state regulators at the New Hampshire Public Utilities Commission (PUC) approve passing the cost on to ratepayers, the energy rates for PSNH customers – already the highest in New Hampshire by a wide margin – will go up by at least 1.2 cents per kilowatt hour, or almost 15%.  CLF is seeking to intervene in the PUC proceeding on the rate increase.  PSNH, unsurprisingly, wants to keep CLF out, in addition to any other party seeking to intervene on behalf of ratepayers.  There is no better illustration of the folly – for ratepayers and the environment alike – of major new investments in coal-fired power plants than PSNH’s flawed effort to extend the life of Merrimack Station.  These investments are a disaster for ratepayers, and don’t even ensure compliance with the plant’s environmental requirements – a case CLF is making right now in federal court with regard to other modifications to Merrimack Station.
  • Large commercial and industrial customers with the buying power to avoid the high rates for PSNH’s fossil power continue to do so in dramatic numbers.  PSNH announced that, in September, about 82% of these customers were buying power elsewhere in the market (accounting for 93% of the power delivered to these customers) – a phemonenon known as “migration.”  Meanwhile, more than 99% of New Hampshire residents in PSNH territory were left behind to pay PSNH’s already exorbitant rates.  The scrubber rate increase is going to make this situation even worse for residents – additional businesses will find other suppliers and PSNH will need to jack up its rates even more.  More cost-effective competitive suppliers are cleaning PSNH’s clock among large customers.  Given the company’s excessive and increasing rates, residential ratepayers are starting to vote with their pocketbooks for more sustainable energy supplies.
  • It is becoming increasingly clear that the current Northern Pass proposal is designed around PSNH’s bottom line, not the interests of New Hampshire ratepayers.  As we’ve mentioned before, the large customer “migration” problem and its upward pressure on homeowners’ electric bills are likely to get worse with Northern Pass, which would further depress regional wholesale electric rates and encourage more customers to leave PSNH.   Adding in the cost of the scrubber will only widen the divide between the businesses that can choose other suppliers and potentially benefit from Northern Pass, and the residential customers who are currently  stuck with PSNH. A new wrinkle emerged last week – testimony from PUC staff showing that PSNH’s consultants estimated a year ago that Northern Pass will cannibalize PSNH’s already meager revenues from Newington Station, PSNH’s little-used power plant in Newington, New Hampshire, that can operate with either oil or natural gas.  Northern Pass would mean it would almost never run and that the investments ratepayers have made over the years to keep Newington Station operating will essentially be lost.  This same dynamic will apply to the rest of PSNH’s power plants:  Northern Pass will diminish their market value further exposing New Hampshire businesses and residents to the risk of excessive costs.  Once again, a series of poor decisions and self-interested advocacy by PSNH (at the expense of ratepayers) is forcing the legislature to intervene.

The costs of PSNH’s coal-fired power plants are becoming untenable, and a radically redesigned Northern Pass proposal and other alternatives could help PSNH meet its customers’ power needs more cheaply and with less damage to public health and the environment.  Instead of planning for a cleaner energy future, PSNH is working only to preserve its regulator-approved profits.  CLF will be using every tool at our disposal to force a rethinking of PSNH’s approach.

Page 2 of 212