CLF Intervenes in Northern Pass Transmission Proceeding


CLF intervened today in proceedings regarding the proposed Northern Pass electricity supply and transmission project in New Hampshire. The proposed project, which involves creating 180 miles of new transmission lines in the state and installing new transmission infrastructure in the White Mountain National Forest, is intended to import 1,200 megawatts (MW) of electricity generated in Canada by Hydro-Quebec, the Canadian public utility. If constructed, the project would have significant impacts on New Hampshire communities and the environment.

CONCORD, NH  December 16, 2010 – The Conservation Law Foundation (CLF) intervened today in the Presidential Permit proceeding recently initiated by the U.S. Department of Energy, for the proposed Northern Pass electricity supply and transmission project.  The proposed project – involving 180 miles of new transmission lines in New Hampshire – is intended to import 1,200 MW of electricity generated by Hydro-Quebec, in Canada.

“This project could profoundly affect New Hampshire’s energy future,” said Jonathan Peress, director of CLF’s Clean Energy and Climate Change program.  “It remains to be seen whether it will help or hinder our efforts in New Hampshire and New England to achieve necessary greenhouse gas reductions and develop a clean energy economy.  Unfortunately, the application is more noteworthy for what it omits, rather than the sparse information it provides.”

The proposed project would include the construction of new transmission corridor in northern-most New Hampshire, as well as the installation of new transmission infrastructure through the White Mountain National Forest. Read more>>

Focus Areas

Climate Change

Places

New Hampshire

Campaigns


About the CLF Blog

The views and opinions expressed on this blog do not necessarily represent the opinions or positions of Conservation Law Foundation, our boards, or our supporters.