This week consultants hired by the Maine Public Utilities Commission (PUC) concluded that Maine should not enter into contracts to purchase gas pipeline capacity because the costs of doing so would outweigh the benefits to Mainers.

In many ways, this was a foregone conclusion – one that CLF predicted nearly a year ago and that the PUC itself (unofficially) reached before soliciting proposals from pipeline companies and spending taxpayer dollars on a lengthy consultant’s report. It’s a cautionary tale not just for Maine but for all of New England as the region weighs its energy future – and decides whether it will overinvest in natural gas or blaze a trail based on cleaner, renewable resources.

This process all started back in March 2014. After a cold winter sparked region-wide fears of an imminent shortage of natural gas to power our homes and businesses, Maine’s PUC was tasked with determining whether the state should contract for additional gas capacity under the Maine Energy Cost Reduction Act (MECRA). The PUC approached this work in two phases: first, soliciting and examining evidence and testimony from a variety of interested parties, including CLF, as to the need and economics of gas pipeline capacity procurement. And, second, if the economics made sense, to request proposals from pipeline companies.

CLF testified before the PUC as it gathered the evidence and data it would need to make their determination. We reasoned that Maine should not enter into new contracts with pipeline companies – both because the legal basis for them was suspect (the investment in these new projects would have been paid for by ratepayers, which is unprecedented and risky) and because the costs – to our wallets and our climate – would ultimately outweigh the benefits to consumers.

PUC staff agreed with the economic argument in their own preliminary report, but the Commission nonetheless went ahead and accepted supply proposals from pipeline companies. As required by MECRA, the PUC hired an independent consultant, London Economics International (LEI), to examine these proposals. The consultant’s detailed report compared scenarios in which the state didn’t contract for additional pipeline and ones in which it did (based on the actual proposals the state had received).

LEI’s analysis reinforces both CLF’s testimony and comments and the PUC’s own staff report issued during the first phase of this proceeding: The costs of any contract for Maine to buy natural gas pipeline capacity trumps the benefits. In fact, LEI concluded that, even without Maine entering into a gas contract, gas prices should drop by 25% for Maine customers over the next few years due to already planned, market-based gas capacity expansions. The group also found that electricity prices should drop by 15% due to these lowering gas prices.

The LEI report rightly calls into question whether the PUC should have accepted proposals from gas companies in the first place – a process that has been costly to all participants, expended valuable resources of the PUC, and resulted in no different a conclusion than the PUC’s own staff analysis.

Maine law requires that, for any contracts like these proposed expansions, the benefits must outweigh the costs. The conclusions drawn by the PUC’s expert consultant in their report should prevent Maine from entering into such a contract any time soon.

Ultimately, there’s a larger lesson here – one for every state in the region considering its electricity future. Over this year-long process, the PUC spent hundreds of thousands of (tax-payer) dollars on experts and an intense, litigation-like process, only for their experts to conclude what was readily apparent at the outset – that subsidizing the gas industry on the backs of ratepayers is a bad idea, both economically and for the environment.

Those gas shortage fears that sparked this whole process in the first place ended up being completely unfounded over this past winter. Since then the economics of the energy markets have started to shift, with wholesale electric prices declining by 50% over the past year alone. Meanwhile, energy efficiency is decreasing the need for energy resources, fuel-free renewables are supplanting polluting power plants, and liquefied natural gas has become cost-competitive and available at times of peak need. With at least two new small-scale pipeline projects already set to come on-line and reduce energy costs even more over the next two years, now is the time for the New England states to invest in the stability of the cleanest energy future we can create – one that weans us off of natural gas within the next 35 years.

Focus Areas

Climate Change

Places

Maine

Campaigns

Energy Efficiency

Leave a Reply

About the CLF Blog

The views and opinions expressed on this blog do not necessarily represent the opinions or positions of Conservation Law Foundation, our boards, or our supporters.